Angolan rare earth project construction progressing
IN FOR THE LONG HAUL The construction at Pensana's Longonjo project in Angola will take the mine through to a projected life of 20 years
Magnet metals miner Pensana, continuing with the site development works for its rare-earth elements Longonjo project, in Angola, reported towards the end of August that it was progressing with site infrastructure development underway, in preparation for main construction.
Being largely unaffected by its revised development strategy, which was announced in June, Pensana reported that the Longonjo site development included earthworks, which were being undertaken by Portuguese construction and related services group Group Nov, while electrical reticulation was being conducted by Angolan electrical project house Elecktra.
Pensana was also undertaking water and sewerage services in preparation for the mining camp construction.
At the time, the miner also noted that consultancy SRK was making good progress on the geotechnical investigations in support of Longonjo’s dual purpose tailings storage facility’s (TSF’s) detailed design.
The selected TSF site was confirmed as providing suitable excavated material for use in the TSF starter walls, pit haul roads, plant terracing and other construction-related requirements, thus mitigating visual impact and the need to develop borrow-pit sources and associated licensing and material transport costs.
Further, Pensana also noted that it was continuing with the integration of the Longonjo project’s bulk reagent consumption requirements, for sulphur and caustic soda, using commodities supplier Trafigura- and multi-disciplinary construction and related services firm Mota Engil-led port and rail concessions for the strategic mineral-focussed Lobito Corridor, as part of the ongoing operation-readiness preparations of the Longonjo project.
In this regard, Pensana reported that logistical and operational expenditure benefits were obvious in terms of broader reagent supply to the existing Democratic Republic of Congo Copperbelt mines, alongside limestone, which will be sourced from the existing quarries in the Lobito area of Angola.
Engineering Developments
In line with its mid-year revised financing and development strategy, Pensana reported that the revised process plant design for the Longonjo project was based on a scaled-down version of the existing processing route with revised mining, comminution, flotation, thickening, calcining, leaching and product precipitation throughput rates.
The revised financing and development strategy will see Longonjo fully funded into production on a staged basis, with the upfront capital expenditure reduced to $200-million.
Pensana CEO Tim George says the project team is on schedule with the stage 1 re-engineering to the $200-million capital expenditure design work and is also well advanced on the financial due diligence for the main financing later this year.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation