Bellevue tracking to plan

22nd December 2022

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Gold developer Bellevue Gold is on track to reach gold production in the second half of 2023, with the first draw down of A$35-million from its project loan facility with Macquarie Bank taking place this week.

“We are in a strong position with the project running comfortably on time and on budget. The strong progress made in recent months, combined with the proceeds of the raising, has enabled us to continue pushing ahead at a rapid pace, further de-risking the project from both a production and timetable perspective,” said MD Steve Parsons.

Recent works include further acceleration of the underground development with a third underground jumbo rig mobilised to site by contractor Develop Global. The jumbo, which is being commissioned and is due to commence work at the start of January 2023, will be used to develop additional access in the Marceline area.

Underground development rates are expected to continue increasing with the ramp up of ore drives starting in the new year.

Overall development rates continue to exceed the project schedule, putting the project well on track to meet commercial production in the second half of calendar year 2023, Bellevue said in a statement.

During the first 12 months of commercial production, the project is forecast to produce between 180 000 oz to 200 000 at an all-in sustaining cost of A$1 000/oz to A$1 100/oz.

Edited by Creamer Media Reporter

Comments

 

Showroom

Weir
Weir

Weir is a global leader in mining technology. We recognise that our planet’s future depends on the transition to renewable energy, and that...

VISIT SHOWROOM 
Weir
Weir

Weir is a global leader in mining technology. We recognise that our planet’s future depends on the transition to renewable energy, and that...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Minerals Council South Africa CEO Mzila Mthenjane
Minerals Council optimistic about ongoing MPRDA review
13th December 2024 By: Marleny Arnoldi
Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.291 0.37s - 164pq - 2rq
Subscribe Now