Construction of South Star’s Brazil graphite mine nearing completion

20th June 2024

By: Creamer Media Reporter

     

Font size: - +

Canada-listed South Star is gearing up for production from the Phase 1 plant of its flagship Santa Cruz graphite mine,  in Brazil, to start in the coming weeks.

Construction of the 1 000-t-a-month plant will be completed this month, followed by an estimated six weeks of commissioning and ramp-up.

South Star provided an update on the project on Wednesday in a statement, which also announced that it had made the final payment for the land purchase required for the Phase 1 mine and plant facilities.

In addition, the definitive mining licence for five areas, totalling 4 431 ha, has been approved by government and three additional claims were in final evaluation.

The approved licences cover the main areas required for Phases 1, 2 and 3 mining operations.

With the land purchased and definitive mining licences granted, the Santa Cruz project was derisked from a permitting and licensing standpoint.

“We have a clear path to scaling production as the markets and our clients ask for additional high-quality Brazilian graphite concentrates,” commented South Star CEO Richard Pearce.

Santa Cruz will be the first new graphite production in the Americas since 1996, with Phase 1 commercial production projected in the third quarter. Phase 2 production (25 000 t/y) is partially funded and planned for 2026, while Phase 3 (50 000 t/y) is scheduled for 2028.

“Our agreement with Sprott already secures approximately 50% of our Phase 2 capital expenditure, and our team is pushing to complete an updated feasibility study on Santa Cruz incorporating Phase 3 production,” added Pearce.

 

Edited by Creamer Media Reporter

Comments

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 21 February 2025
Magazine round up | 21 February 2025
21st February 2025
BOLSTERING PRESENCE
The project is set to bolster Namibia’s position as one of the world’s leading uranium producers
Uranium mine moving closer to production
21st February 2025 By: Simone Liedtke

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.181 0.255s - 180pq - 2rq
Subscribe Now