Midtier precious metals miner Endeavour Silver reported on Friday that its Terronera silver/gold project, in Mexico, is nearing completion, with the company focused on maintaining its construction schedule and momentum for full commissioning.

“Dry commissioning is advancing well on the Upper Platform and we’re completing final installations and the last of the punch list items. Our team’s efforts are concentrated on timely completion of the Lower Platform where structural steel is advancing to install the tailing filters.

“We’re focused on maintaining our construction schedule and momentum to have Terronera ready for full commissioning in early second-quarter 2025,” said COO Don Gray.

Meanwhile, Endeavour Silver also updated its capital expansion cost for the project, stating that it would cost $332-million, compared with the 2024 estimate of $271-million.

Edited by Creamer Media Reporter

Comments

 

Showroom

Essentra Components
Essentra Components

We are responsible manufacturers of essential components. Manufacturing 80 million parts a week, we have over 1 billion parts in stock.

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 25 April 2025
Magazine round up | 25 April 2025
25th April 2025
Ferrochrome, diamonds, platinum make headlines
Ferrochrome, diamonds, platinum make headlines
24th April 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.131 0.202s - 144pq - 2rq
Subscribe Now