PERTH (miningweekly.com) – Tungsten miner EQ Resources has reported a new monthly record of concentrate production at its Mt Carbine project, in Queensland, following the completion of an upgrade to the power line to the site.
The upgrade has allowed the XRT Sorter at Mt Carbine to operate on a 24-hour basis.
EQ Resources told shareholders on Monday that a successful debottlenecking strategy and Early Works investment targeting the crushing, screening and XRT sorting capacity contributed to the production of a record of more than 40 t of 50% tungsten concentrate in December, showing the positive impact of the continuous improvements at Mt Carbine.
EQ Resources and its joint venture (JV) partner, global metals group Cronimet, began re-commissioning the historical processing plant in 2020, with a further significant investment to upgrade the processing capacity at Mt Carbine early in 2021 as part of the staged development plan for the site.
The JV has also integrated advanced Tomra XRT ore-sorting technology into the crushing and screening flowsheet with the dual target of producing a tungsten concentrate and creating a barren green aggregate by-product stream from waste rock from the ore-sorting process. Extensive field-based test work was conducted throughout 2021, with a tenfold upgrade in the low-grade ore achieved consistently over production trials.
“Mt Carbine is ramping up production into a firm market for tungsten concentrates and a strong, stable price for the major end product ammonium paratungstate, currently around $325/MTU, compared with $230/MTU a year ago,” said EQ Resources CEO Kevin MacNeill.
“We are expanding our production and expanding our team at Mt Carbine as we create a sustainable mine for the future. We are delivering concentrates for the global market and re-purposed waste rock as by-product aggregates for the local market.
“With the early works being completed in the coming weeks, we see ourselves right on target with the production upgrade towards some 90 t of concentrate per month.”
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation