Gamsberg smelter project, South Africa – update

Image of the Gamsberg mine

Photo by Vedanta Zinc International

28th June 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Gamsberg smelter project.

Location
Northern Cape, South Africa.

Project Owner/s
Vedanta Zinc International (VZI).
 
Project Description
The Gamsberg smelter plans to treat all zinc concentrate from the Gamsberg operation. 

A phased approach will be used. 

In Phase 1, 300 000 t/y will be processed by repeating the available Hindustan Zinc Limited, or HZL, smelter design incorporating the necessary modifications required to treat Gamsberg concentrate. 
 
Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
Planned first production is expected in the 2029/30 financial year.

Latest Developments
Partner selection is in progress for various engineering, procurement and construction packages. 

The construction tender was in November 2022.

Key Contracts, Suppliers and Consultants
TKIS-India (owner’s engineer); and Shapoorji & L&T (prospective engineering and procurement partners).

Contact Details for Project Information
VZI, tel +27 11 685 3960 or email info@vedantaresources.co.za.

Edited by Creamer Media Reporter

Comments

 

Showroom

Weir
Weir

Weir is a global leader in mining technology. We recognise that our planet’s future depends on the transition to renewable energy, and that...

VISIT SHOWROOM 
Avlock International
Avlock International

Avlock International is a leading manufacturer and distributor of Specialized Fastening Systems.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Minerals Council South Africa CEO Mzila Mthenjane
Minerals Council optimistic about ongoing MPRDA review
13th December 2024 By: Marleny Arnoldi
Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.101 0.234s - 127pq - 2rq
Subscribe Now