Giyani’s water thirst to be quenched by end-September

29th August 2025

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

     

Font size: - +

The Giyani Water Intervention Programme, in Limpopo province’s Mopani district, is expected to be completed before the end of September 2025.

Currently 90.23% complete, the long- delayed Giyani water services project includes the construction of 325 km of bulk pipelines from the Giyani water treatment works to the service reservoirs that will supply water to 55 villages in Giyani.

Pressure testing and commissioning account for nearly 90% of the remaining works to be completed.

A Cabinet brief in early August outlined that 23 of the 24 villages under the Giyani 55 Villages Reticulation Phase 1 now have reticulation and household connections.

The first phase entails reticulation and household metered connections to 24 of the 55 villages.

Phase 2a, which involves the reticulation and metered household connections to 15 villages, will be implemented in the 2025/26 financial year, and Phase 2b, incorporating 16 villages, will be implemented in the outer year of the medium-term expenditure framework.

The upgrade of the Giyani water treatment works from 30-million litres a day to 40-million litres a day and the development of several well fields to ensure sufficient water supply to the 55 villages in Giyani is still at the planning stage and will be implemented in the third quarter of the current financial year.

This follows on previous significant interventions, including the refurbishment of the Giyani water treatment works to restore its original production capacity to 30-million litres a day, after falling to between 13-million and 17-million litres a day, was completed in June 2024.

Further, practically completed in December 2023 after becoming functional in April 2023, the Nandoni-Nsami bulk pipeline – a 40.5 km raw water pipeline from Nandoni dam in Vhembe – currently supplies the Giyani water treatment works with an average of 15-million litres of raw water a day.

The completed projects cost an estimated R6-billion, funded by the Department of Water and Sanitation.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 
John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (29/08/2025)
29th August 2025 By: Martin Creamer
Magazine round up | 29 August 2025
Magazine round up | 29 August 2025
29th August 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.082 0.16s - 126pq - 2rq
Subscribe Now