Hemerdon tungsten and tin project, England
Name and Location
Hemerdon tungsten and tin project, England.
Client
Wolf Minerals.
Project Description
The Hemerdon project is located about 9.6 km north-east of Plymouth, near Plympton, in Devon.
The project includes a two-stage openpit, with a ten-year life and a three-million-tonne-a-year concentrator, with associated infrastructure.
Mining will be performed by a mining contractor using conventional hydraulic excavator and truck operations.
The proposed processing facility will separate the wolframite (tungsten) and the cassiterite (tin) from the gangue using crushing, screening and scrubbing; dense-medium separation; desliming and gravity separation; concentrate processing; tailings thickening and disposal.
Value
£123.2-million.
Duration
Production is expected to start in 2015.
Latest Developments
Wolf Minerals has secured a power supplier for its Drakelands openpit tungsten/tin project, which forms part of the greater Hemerdon project in England.
DONG Energy has been awarded the contract to supply grid power to the Drakelands mine, following a tender process.
Under the terms of the contract, DONG will supply a projected 82 GWh to the operation, for a three-year period.
Key Contracts and Suppliers
GR Engineering (engineering, procurement and construction contract) and CA Blackwell (mining services contract).
On Budget and on Time?
The project remains on schedule to start earthworks this month, with construction scheduled during the second quarter of 2014. Tungsten production is expected to start in 2015.
Contact Details for Project Information
Wolf Minerals, +61 8 6364 3776, fax +61 8 6210 1872 or email admin@wolfminerals.com.au.
GR Engineering, tel +61 8 6272 6000, fax +61 8 6272 6001 or email gres@gres.com.au.
CA Blackwell, tel +44 1787 223131, fax +44 1787 223235 or email enquiries@cablackwell.co.uk.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation