Innovative removal of raisebore head helps keep Platreef on track

Murray & Roberts Cementation completed the raiseboring of the mine’s Shaft 2 last year; the shaft will be the primary production shaft for extracting ore from underground operations

Murray & Roberts Cementation successfully developed and applied an innovative method to remove the raisebore head and base at Ivanplats’ Shaft 2

Murray & Roberts Cementation’s rigging specialist developed a concept using a reeve block system and a winch positioned at the bank elevation, designed to be secured with minimal steelwork

The reeve blocks were secured to the internal headgear steelwork using slings and beam clamps, while an eight tonne electric winch, anchored at the bank, was used to operate the reeve block system

This approach enabled the hoisting of the raisebore machine and all its components to the bank area, where they were positioned on the support bridge and subsequently moved out of the shaft headgear

Murray & Roberts Cementation successfully completed the removal of the raisebore machine safely and efficiently within the demanding timeframe

14th April 2025

     

Font size: - +

At the end of the raiseboring – or reaming – stage for Shaft 2 of Ivanplats’ Platreef project in South Africa’s Limpopo province, an innovative solution was called for to promptly remove the reaming head and avoid costly standing time.

Fred Durand, Senior Project Manager at Murray & Roberts Cementation, explains that an acceleration of the build plan at Shaft 2 had seen construction underway on the shaft’s headgear in 2024 – before the completion of raiseboring.

“When a reaming head reaches the surface at the end of a raiseboring process, we normally use a mobile crane from surface to help us dismantle the machine and to load it onto trucks for removal from site,” says Durand. “With the acceleration of the mine’s plan for Shaft 2 readiness, however, the construction of the headgear had been brought forward – so it was no longer feasible to position a crane in that area to remove the raisebore machine.”

“The kibble winder was not installed yet, so we had to engineer our way out of this situation to reduce raisebore standing time costs,” he says.

The solution began with a visit from one of Murray & Roberts Cementation’s rigging specialists from the company’s Bentley Park training and technical facility near Carletonville. His concept was to make use of a reeve block – or pulley block – system and winch which could be secured with limited steel work at the bank elevation.

“We prepared a proposal which described how reeve blocks could be secured to the sinking sheave wheel floor steel work by means of slings and beam clamps,” Durand continues. “We would then use an eight tonne electrical winch, secured to the bank, to operate the reeve block system.”

After the Murray & Roberts Cementation team were satisfied that the methodology would work, they conducted a rigorous risk assessment and prepared the necessary mitigation measures. The plan was then ready for the client’s consideration – leading to a green light to proceed. Personnel and equipment were soon mobilised, and the necessary medicals and inductions completed in preparation for the reamer coming to surface at the end of its 950 m journey from underground.

“Our solution worked perfectly, allowing us to strip the raisebore machine and hoist it to the bank area – to be placed onto the support bridge and moved out of the shaft headgear,” he says. “A mobile crane then lifted the machine onto the laydown area, ready for removal.”

Durand concludes that Murray & Roberts Cementation’s uncompromising approach to safe working practices ensured that this engineering solution was applied safely and efficiently within the tight timeframe. The company’s core safety values recently earned it the landmark achievement of 8 million fatality free shifts.

Edited by Creamer Media Reporter

Comments

Latest News

De Grey's Hemi gold project
Gold Road backs Northern Star’s De Grey takeover
14th April 2025 By: Mariaan Webb
An image of metal pieces
Mining production, sales fall in February
15th April 2025 By: Tasneem Bulbulia

Showroom

John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 
BOVA Safety Wear
BOVA Safety Wear

BOVA cemented their reputation in Africa by delivering high quality engineering through their range of safety footwear. 21 years after producing...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Martin Creamer and Francisco Baudrand
Enaex Africa transforms beyond compliance
14th April 2025
Photo of Martin Creamer
On-The-Air (11/04/2025)
11th April 2025 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.129 0.202s - 134pq - 2rq
Subscribe Now