Innovative removal of raisebore head helps keep Platreef on track







Murray & Roberts Cementation completed the raiseboring of the mine’s Shaft 2 last year; the shaft will be the primary production shaft for extracting ore from underground operations
Murray & Roberts Cementation successfully developed and applied an innovative method to remove the raisebore head and base at Ivanplats’ Shaft 2
Murray & Roberts Cementation’s rigging specialist developed a concept using a reeve block system and a winch positioned at the bank elevation, designed to be secured with minimal steelwork
The reeve blocks were secured to the internal headgear steelwork using slings and beam clamps, while an eight tonne electric winch, anchored at the bank, was used to operate the reeve block system
This approach enabled the hoisting of the raisebore machine and all its components to the bank area, where they were positioned on the support bridge and subsequently moved out of the shaft headgear
Murray & Roberts Cementation successfully completed the removal of the raisebore machine safely and efficiently within the demanding timeframe
At the end of the raiseboring – or reaming – stage for Shaft 2 of Ivanplats’ Platreef project in South Africa’s Limpopo province, an innovative solution was called for to promptly remove the reaming head and avoid costly standing time.
Fred Durand, Senior Project Manager at Murray & Roberts Cementation, explains that an acceleration of the build plan at Shaft 2 had seen construction underway on the shaft’s headgear in 2024 – before the completion of raiseboring.
“When a reaming head reaches the surface at the end of a raiseboring process, we normally use a mobile crane from surface to help us dismantle the machine and to load it onto trucks for removal from site,” says Durand. “With the acceleration of the mine’s plan for Shaft 2 readiness, however, the construction of the headgear had been brought forward – so it was no longer feasible to position a crane in that area to remove the raisebore machine.”
“The kibble winder was not installed yet, so we had to engineer our way out of this situation to reduce raisebore standing time costs,” he says.
The solution began with a visit from one of Murray & Roberts Cementation’s rigging specialists from the company’s Bentley Park training and technical facility near Carletonville. His concept was to make use of a reeve block – or pulley block – system and winch which could be secured with limited steel work at the bank elevation.
“We prepared a proposal which described how reeve blocks could be secured to the sinking sheave wheel floor steel work by means of slings and beam clamps,” Durand continues. “We would then use an eight tonne electrical winch, secured to the bank, to operate the reeve block system.”
After the Murray & Roberts Cementation team were satisfied that the methodology would work, they conducted a rigorous risk assessment and prepared the necessary mitigation measures. The plan was then ready for the client’s consideration – leading to a green light to proceed. Personnel and equipment were soon mobilised, and the necessary medicals and inductions completed in preparation for the reamer coming to surface at the end of its 950 m journey from underground.
“Our solution worked perfectly, allowing us to strip the raisebore machine and hoist it to the bank area – to be placed onto the support bridge and moved out of the shaft headgear,” he says. “A mobile crane then lifted the machine onto the laydown area, ready for removal.”
Durand concludes that Murray & Roberts Cementation’s uncompromising approach to safe working practices ensured that this engineering solution was applied safely and efficiently within the tight timeframe. The company’s core safety values recently earned it the landmark achievement of 8 million fatality free shifts.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation