Iron Bridge magnetite project – Stage 2, Australia – update

Iron Bridge magnetite project – Stage 2, Australia – update

Photo by FMG

5th March 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Iron Bridge magnetite project – Stage 2.

Location
The project is located 145 km south of Port Hedland, in Pilbara, Western Australia.

Project Owner/s
The project is owned through an unincorporated joint venture between Fortescue Metals Group subsidiary FMG Iron Bridge, or FMG IB (69%), and Formosa Steel (31%).

FMG will manage and operate the project with full marketing rights.

Project Description
The project has a mineral resource of 5.45-billion tonnes, including an ore reserve of 716-million tonnes. 

The project has a mine life of more than 20 years.

This Stage 2 development follows the $500-million investment in the successful Stage 1 construction of large-scale pilot and demonstration plants, which have validated key equipment and magnetite production processes for the full-scale Stage 2 ore processing facility.

Stage 2 development includes:

• a 22-million-wet-metric-tonnes-a-year ore processing facility (once at full operational capacity);

• an airstrip and expanded village;

• a 195 km canning basin water pipeline;

• a 135 km concentrate pipeline to FMG’s Herb Elliot port facility, in Port Hedland, and a return process water pipeline; and

• port handling facilities, including concentrate dewatering, covered storage and reclaiming/conveying, to existing port outload circuits.

The project aims to produce 22-million wet metric tonnes a year once full operational capacity is achieved. Iron Bridge will deliver a premium product with an iron content of 67%.

Potential Job Creation
About 3 000 people will be employed during construction and 900 full-time positions will be created once operations start.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
A review of the project has upwardly revised the capital cost of the project from $2.6-billion to $3-billion.

Planned Start/End Date
First production is scheduled for 2022.

Latest Developments
Iron-ore miner Fortescue Metals has postponed first production from its Iron Bridge magnetite mine.

First production is now expected in the second half of 2022, as opposed to the first half.

A technical and commercial assessment of the project is under way, and is scheduled to take about 12 weeks to complete.

The assessment will focus on enhancing the use of Fortescue’s port and rail infrastructure for the project, assessing the magnetite concentrate transportation solution and return water pipelines to Port Hedland, contractor strategy and selection, and the logistics infrastructure to maintain the scheduled delivery of the large modular components through Port Hedland.

Key Contracts, Suppliers and Consultants
NRW Holdings (bulk earthworks).

Contact Details for Project Information
Fortescue, tel +61 8 6218 8888.
Formosa Steel, tel +886 2 2712 221.

 

Edited by Creamer Media Reporter

Comments

Latest Multimedia

Latest News

Magazine round up | 18 April 2025
Magazine round up | 18 April 2025
18th April 2025

Showroom

Goodwin Submersible Pumps Africa (Pty) Ltd
Goodwin Submersible Pumps Africa (Pty) Ltd

Goodwin Submersible Pumps Africa is sole distributors for Goodwin electrically driven, submersible, abrasion resistance slurry pumps.

VISIT SHOWROOM 
Flameblock
Flameblock

FlameBlock is a proudly South African company that engineers, manufactures and supplies fire intumescent and retardant products to the fire...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hillside Aluminium smelter in South Africa’s KwaZulu-Natal.
Hillside Aluminium guiding unchanged output for 2025 financial year
17th April 2025 By: Martin Creamer
Andrada CEO Anthony Viljoen.
Andrada looking to opening more mines in Namibia
16th April 2025 By: Martin Creamer
Resources Watch
Resources Watch
16th April 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.116 0.249s - 130pq - 2rq
Subscribe Now