Kamoa-Kakula nears completion of Phase 1 ramp-up
TSX-listed Ivanhoe Mines and Zijin Mining Group’s joint Kamoa-Kakula project, in the Democratic Republic of Congo, produced 14 815 t of copper in August, bringing the year-to-date production to more than 36 700 t.
The company is ramping up the mine’s 3.8-million-tonne-a-year Phase 1 concentrator plant to reach nameplate steady state capacity, alongside a Phase 2 concentrator plant that is being built.
Ivanhoe confirms that construction on the second concentrator plant is about 44% complete and will be fully completed by the third quarter of next year.
The company also announces that six new turbines are operational at the Mwadingusha hydropower plant in the country and are supplying clean electricity for Kamoa-Kakula.
Kamoa Copper – the operating company – is fast-tracking the installation of an additional concentrate filter on the Phase 1 plant, which should enable the concentrator to produce more copper than its design capacity of about 200 000 t/y.
The mine is projected to produce between 80 000 t and 95 000 t of copper this year and, ultimately, to reach peak copper production of more than 800 000 t/y in due course.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation