Kamoa-Kakula sets new monthly copper production record

3rd December 2024

By: Darren Parker

Creamer Media Senior Contributing Editor Online

     

Font size: - +

The Phase 1, 2, and 3 concentrators at the Kamoa-Kakula copper complex in the Democratic Republic of Congo (DRC) have set a new monthly production record in November, with TSX- and OTCQX-listed Ivanhoe Mines reporting combined production of 45 019 t of copper in concentrate.

The concentrators processed 1.2-million tonnes of ore, achieving an average feed grade of 4.58% copper. Total copper production from Kamoa-Kakula for the year to November 30 now stands at 390 061 t.

The recently commissioned Phase 3 concentrator performed well, achieving an average recovery rate of 85.3% in November, close to its design target of 86%. On November 26, it set a record with a 90% recovery rate over a 24-hour period.

“Kamoa-Kakula’s production continues to accelerate into year-end, following the ramp-up of the Phase 3 concentrator earlier this quarter. November marked another significant milestone with a 10% month-on-month increase in copper production, taking the annualised production rate to [about] 550 000 t of copper.”

“There is much more copper to come from this world-class mining district as we advance towards our production capacity of 600 000 t/y . . . Just three and a half years ago, we produced our first copper,” Ivanhoe founder and executive co-chairperson Robert Friedland said on December 3.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Latest News

Greatland-Newmont deal to close this week
Greatland-Newmont deal to close this week
3rd December 2024 By: Mariaan Webb

Showroom

Avlock International
Avlock International

Avlock International is a leading manufacturer and distributor of Specialized Fastening Systems.

VISIT SHOWROOM 
Rio-Carb
Rio-Carb

Our Easy Access Chute concept was developed to reduce the risks related to liner maintenance. Currently, replacing wear liners require that...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.135 0.211s - 149pq - 2rq
Subscribe Now