https://newsletter.mw.creamermedia.com
Africa|Construction|Consulting|Contractor|Design|Engineering|Exploration|Financial|Gold|Infrastructure|Mining|PROJECT|Resources|SECURITY|Services|Storage|Testing|Solutions|Environmental|Drilling|Infrastructure|Operations
Africa|Construction|Consulting|Contractor|Design|Engineering|Exploration|Financial|Gold|Infrastructure|Mining|PROJECT|Resources|SECURITY|Services|Storage|Testing|Solutions|Environmental|Drilling|Infrastructure|Operations
africa|construction|consulting-company|contractor|design|engineering|exploration|financial|gold|infrastructure|mining|project|resources|security|services|storage|testing|solutions|environmental|drilling|infrastructure|operations

Kobada gold project, Mali – update

LOcation map of the Kobada project

Photo by Toubani Resources

14th November 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Kobada gold project.

Location
Southern Mali.

Project Owner/s
Africa-focused gold developer Toubani Resources and 35% shareholder Eagle Eye Assets (EEA).

Project Description
A definitive feasibility study (DFS) completed in October 2024 has confirmed Kobada as a significant gold development asset underpinned by its large-scale, free-dig and open-pittable oxide resource.

The ore reserve estimate is 53.8-million tonnes at 0.90 g/t for 1.56-million ounces of gold.

The DFS proposes average production of 162 000 oz/y over the current 9.2-year life-of-mine for total gold production of 1.49-million ounces of gold.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of $870-million and an internal rate of return of 72%, with a payback of 1.25 years.

Capital Expenditure
The October 2024 DFS estimates total initial development capital of $216-million.

Planned Start/End Date
First gold production is targeted for the third quarter of 2027. 

Latest Developments
Toubani Resources has stated that operations at the project remain unaffected by recent fuel supply restrictions and security concerns reported in the country’s capital, Bamako.

Drilling activities are continuing as planned, with a second reverse-circulation rig expected on site shortly to accelerate anomaly testing and sterilisation programmes ahead of finalising infrastructure locations. Other project-readiness activities are advancing while the Bamako office continues to operate normally.

Following approval of the Kobada environmental- and social-impact assessment in October, Toubani is progressing with permitting activities, maintaining close engagement with authorities and stakeholders. The company has appointed Ausenco Services as its engineering, procurement and construction management contractor, with initial engineering work under way and long-lead orders placed.

Toubani's licence for the project remains in good standing, and discussions with Malian authorities on completing the investment framework are advancing.
In addition, Toubani shareholder EEA has reaffirmed its support. 

“We look forward to supporting Toubani in progressing key project milestones in the near term and finalising its funding arrangements, which includes EEA’s significant A$70-million follow-on equity investment and $160-million gold stream.”

Upon completion of the funding package, Toubani expects to hold A$177-million in cash, before any drawdown from the $160-million gold stream.

Key Contracts, Suppliers and Consultants
Ausenco (engineering, procurement, and construction management contractor); Minxcon Group South Africa (mineral resource estimate); DRA Americas (mining and mineral reserves); Maelgwyn Mineral Services (metallurgical testwork); ABS-Africa (environmental and social studies); Epoch Resources (tailings storage facility); SENET (processing plant and infrastructure, including economic valuation and report compilation); Knight Piésold (DFS – tailings dam design and costing); Global Commodity Solutions (DFS – geology and exploration); Entech (DFS – mineral resources); Oreology (DFS – pit optimisations, mine design and mine scheduling); Minero Consulting (DFS – mining operating and capital cost estimation, and ore reserves); Lycopodium (DFS – metallurgical testwork review, process plant design, process plant operating and capital cost estimation); ABS Africa (DFS – environmental and social impact); Anandarasa Advisory (DFS – financial modelling); and Cantilever Future Solutions (DFS – study management and environmental, social and governance oversight); and Endeavour Financial (financial adviser).

Contact Details for Project Information
Toubani Resources, email info@africangoldgroup.com.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Comments

Showroom

Trotech
Trotech

Design, Construction and Maintenance of Site Erected, Welded Bulk Storage Tanks for the Petrochemical, LNG, Ammonia and Sustainable fuel Sectors.

VISIT SHOWROOM 
Virtual Gas Network (Pty) Ltd
Virtual Gas Network (Pty) Ltd

Virtual Gas Network supplies compressed natural gas via a virtual gas distribution network.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 14 November 2025
Magazine round up | 14 November 2025
14th November 2025
Golden City being put back on gold map by exciting new West Wits gold project; and, Thungela highlights innovation, talent, sustainability in coal processing at Coal Africa 2025
Resources Watch
12th November 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.14 0.282s - 131pq - 2rq
Subscribe Now