Langer Heinrich uranium restart project, Namibia – update
Langer Heinrich mine
Photo by ©Bloomberg
Name of the Project
Langer Heinrich uranium restart project.
Location
Namib Desert, Namibia.
Project Owner/s
Langer Heinrich Mauritius Holdings is the holding company of Langer Heinrich Uranium, which holds 100% of the Langer Heinrich tenements.
Paladin Energy owns 75% of Langer Heinrich Mauritius Holdings, with 25% owned by CNNC Overseas Uranium Holdings.
Project Description
Langer Heinrich has an estimated 17-year mine life, supported by ore reserves of 84.8-million tonnes with an average uranium grade of 448 parts per million.
Life-of-mine production is estimated at 77.4-million pounds of uranium, up from a previously stated 76.1-million pounds.
Langer Heinrich was placed on care and maintenance in August 2018, owing to the sustained low uranium price.
Paladin completed a concept study in February 2019, which identified multiple options to reduce operating costs, improve process plant performance and potentially recover a saleable vanadium product.
A two-stream prefeasibility study (PFS1 and PFS2) was started in March 2019 to improve the details of the restart plan and pursue further improvement options to clearly present a compelling investment case.
PFS1 focused on confirming effective care and maintenance plans, practices and costs while developing a more detailed plan to execute a rapid restart at Langer Heinrich in an improved uranium market.
Potential Job Creation
The project will employ about 300 staff.
Net Present Value/Internal Rate of Return
Not stated.
Capital Expenditure
Paladin is forecasting total capital costs of about $125-million, from the previous forecast of $118-million.
Planned Start/End Date
The project restarted commercial production on March 30, 2024, following the successful completion of the restart project. The mine will be in operational ramp-up during the 2025 financial year, with ore feed to the plant sourced from previously mined stockpiled ore.
Production levels are expected to be higher in the second half of the year. Mining activities are expected to restart in the 2026 financial year, ahead of achieving nameplate production of six-million pounds a year by the end of 2026.
Latest Developments
Paladin has revised downwards its production forecast for the Langer Heinrich mine.
The company cited weaker-than-expected performance in October and ongoing challenges in ramping up operations as key factors behind the revised guidance.
Paladin now expects to produce between 3-million and 3.6-million pounds of uranium from Langer Heinrich in the 2025 financial year, compared with its previous forecast of 4-million to 4.5-million pounds.
Paladin has also announced a two-week planned shutdown at the mine to conduct operational improvements and upgrades aimed at addressing production challenges.
Langer Heinrich is in the midst of a 21-month ramp-up period, with the mine now about seven months into the process.
Paladin has emphasised that production is expected to rise as the ramp-up progresses and higher-grade ore is processed in the latter half of the 2025 financial year.
“The company remains confident that, by the end of 2025, Langer Heinrich will achieve a production run rate of 6-million pounds per year,” Paladin said in a statement on November 12.
Key Contracts, Suppliers and Consultants
None stated.
Contact Details for Project Information
Paladin Energy, tel +61 8 9381 4366 or email paladin@paladinenergy.com.au.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation