JSE-listed Mantengu Mining has successfully commissioned the first of three chrome processing plants at its Langpan mining operation, in Limpopo.

The commissioning of the first plant follows 18 months of preparatory work, including a competent person's report and the appointment of Jacques Pretorius as Langpan’s GM.

Pretorius has more than 30 years’ experience in the mining industry and, notably, helped reopen Northam Platinum’s Eland platinum mine, which is located on the western limb of the Bushveld Complex.

The competent person's report estimates the Langpan chrome reserve at 2.17-million tonnes, which underpins the operations’ valuation at R851-million.

Mantengu group CEO Mike Miller says the initial chrome plant was originally designed to accommodate a production throughout of 30 000 t a month, or 70 t/h. The commissioning of the new chrome plant has, however, enhanced production capacity to a throughput rate of 36 000 t a month, or 100 t/h.  

The plant is expected to produce about 18 000 t of chrome concentrate every month, with a chrome content of between 42% and 44%.

The first deliveries of chrome concentrate from the plant are expected on or about June 8.

The other chrome processing plants will consist of a spiral processing and jigging processing plant, respectively. The second plant has a planned production capacity of 30 000 t a month, while the third plant’s production capacity will be 14 000 t a month.

Mantengu plans to commission both plants in August.

 

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Latest News

Showroom

Weir
Weir

Weir is a global leader in mining technology. We recognise that our planet’s future depends on the transition to renewable energy, and that...

VISIT SHOWROOM 
Alcohol Breathalysers
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 21 February 2025
Magazine round up | 21 February 2025
21st February 2025
BOLSTERING PRESENCE
The project is set to bolster Namibia’s position as one of the world’s leading uranium producers
Uranium mine moving closer to production
21st February 2025 By: Simone Liedtke

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.054 0.124s - 139pq - 2rq
Subscribe Now