https://newsletter.mw.creamermedia.com
Construction|Copper|Design|electrification|Energy|Engineering|generation|Gold|Infrastructure|Mining|Platinum|PROJECT|Projects|rail|Resources|Road|Services|Storage|System|Water|Infrastructure|Operations
Construction|Copper|Design|electrification|Energy|Engineering|generation|Gold|Infrastructure|Mining|Platinum|PROJECT|Projects|rail|Resources|Road|Services|Storage|System|Water|Infrastructure|Operations
construction|copper|design|electrification|energy|engineering|generation|gold|infrastructure|mining|platinum|project|projects|rail|resources|road|services|storage|system|water|infrastructure|operations

Marathon palladium/copper project, Canada – update

LOCATION MAP OF THE MARATHON COPPER/PALLADIUM PROJECT

Photo by Generation Mining

11th October 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Marathon palladium/copper project.

Location
Marathon, in north-western Ontario, Canada.

Project Owner/s
The project is a joint venture (JV) between Generation Mining (Gen Mining), which owns an 80% interest in the project, with the remaining interest owned by Sibanye-Stillwater.

Project Description
The proposed mine is expected to produce an average of 166 000 oz of payable palladium and 41-million pounds of payable copper a year over a 13-year life-of-mine (LoM). Over the LoM, the project is expected to produce 2.12-million ounces of palladium, 517-million pounds of copper, 485 000 oz of platinum, 158 000 oz of gold and 3.16-million ounces of silver in payable metals.

The project includes the construction, operation, decommissioning and remediation of three openpits to produce copper concentrate, consisting primarily of copper, palladium and platinum, as well as critical minerals. It also includes an on-site ore processing facility, a 115 kV transmission line, an access road, a mine rock storage area, a process solids management facility and a water management system. 

The process plant throughput starts at 9.2-million tonnes a year, increasing to 10.1-million tonnes a year following the completion of the powerline upgrade scheduled in Year 2 of operations. The increase in process plant throughput is possible with the inclusion of the Hycroft mills in the plant design. 

The process plant will produce a copper/palladium concentrate. The concentrate will be delivered to a third-party facility for further downstream processing into refined critical minerals.  

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a net present value of C$1.16-billion using a 6% discount rate, with a payback of 2.3 years and a robust internal rate of return of 25.8%, based on $1800/oz and $3.70/lb for palladium and copper respectively. 

Capital Expenditure
Initial capital costs are estimated at C$1.11-billion.

Planned Start/End Date.
Gen Mining reported on October 8, 2024, that with all federal approvals for construction having been obtained, and only three outstanding provincial permits expected to be granted by year-end, construction activities could start in 2025.

Latest Developments
Gen Mining has been awarded C$771 000 from the Critical Minerals Infrastructure Fund (CMIF).

The CMIF is a programme under the Canadian Critical Minerals Strategy to address infrastructure gaps, allow for critical minerals production and connect resources to markets through various clean energy, electrification and transportation infrastructure projects.

The funding will be used to advance work on transportation infrastructure while continuing to work towards securing construction financing, Gen Mining president and CEO Jamie Levy has said.

Gen Mining plans to complete engineering and design work, as well as feasibility studies, for road and rail links to support the movement of copper concentrates from the mining project, near Marathon, to smelters in Canada and Europe. As part of this work, the company intends to upgrade the 5 km site access road and develop a new 
4 km access road and transload facility to transfer concentrates.

Key Contracts, Suppliers and Consultants
G Mining Services, with contributions from Ausenco Engineering Canada, Haggarty Technical Services, Knight Piésold, WESC Inc. and P&E Mining Consultants (feasibility study).

Contact Details for Project Information
Gen Mining, tel +1 416 640 0280 or email info@genmining.com. 

Edited by Creamer Media Reporter

Comments

Showroom

Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 21 February 2025
Magazine round up | 21 February 2025
21st February 2025
BOLSTERING PRESENCE
The project is set to bolster Namibia’s position as one of the world’s leading uranium producers
Uranium mine moving closer to production
21st February 2025 By: Simone Liedtke

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.096 0.229s - 129pq - 2rq
Subscribe Now