Minbos flags cost cuts in Angola

23rd February 2023

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – ASX-listed Minbos Resources has flagged a $10-million capital cost saving at its Cabinda phosphate project, in Angola, on the back of a simplified flowsheet.

The company on Thursday reported that following field trials in December last year, which confirmed that phosphate rock from the Cácata mine was suitable as a direct application fertilizer product in most of Angola’s major growing region, the company undertook a review of its production profile.

This review has resulted in a simplified flowsheet to produce a beneficiated phosphate rock (BPR) with the core plant consisting of the crusher, dryer and a bagging plant, and resulting in a cost saving of $10-million.

Minbos noted that the simplified flowsheet was also expected to result in lower operating costs owing to lower energy, maintenance and fixed cost requirements.

The project life at Cabinda is currently estimated at 20 years based on the defined ore reserve, with a production schedule outlined in the definitive feasibility study (DFS) envisaging a ramp-up to full production of the facility over seven years.

The recently completed DFS estimated a capital requirement of $48.5-million to develop the project. The DFS is based on a 187 500 t/y operating capacity, delivering 236 000 t/y of fertilizer over a project life of 20 years, based on a maiden ore reserve of 4.72-million tonnes at 30.1% phosphates at the Cácata phosphate mine.

The base case estimated a post-tax net present value of $203.2-million, an internal rate of return of 39% and a pay-back period of just under five years, with the DFS also estimating average yearly earnings before interest, taxes, depreciation and amortisation of $55-million.

As part of the review, the Minbos completed feasibility work on a Stage 2 expansion for the plant, which is now expected to more than double capacity, with updated capital costs currently being reviewed.

Minbos told shareholders that the company would continue its field trial work with Angola’s national agricultural research and technology development institution Instituto de Investigação Agronómica (IIA), with eight new field trial locations planned over the next four years.

Edited by Creamer Media Reporter

Comments

Showroom

Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 
Goodwin Submersible Pumps Africa (Pty) Ltd
Goodwin Submersible Pumps Africa (Pty) Ltd

Goodwin Submersible Pumps Africa is sole distributors for Goodwin electrically driven, submersible, abrasion resistance slurry pumps.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.151 0.232s - 128pq - 2rq
Subscribe Now