https://newsletter.mw.creamermedia.com
Building|Construction|Contractor|Efficiency|Gold|PROJECT|Steel|Surface|Shaft Sinking|Drilling
Building|Construction|Contractor|Efficiency|Gold|PROJECT|Steel|Surface|Shaft Sinking|Drilling
building|construction|contractor|efficiency|gold|project|steel|surface|shaft-sinking|drilling

Phoenix mine to produce first gold in 2014, capital cost to rise

28th January 2013

By: Natalie Greve

Creamer Media Contributing Editor Online

  

Font size: - +

JOHANNESBURG (miningweekly.com) – TSX- and NYSE-listed Rubicon Minerals on Monday said it expected first production from its Phoenix gold project, in Canada, in the second half of 2014, but warned that, owing to possible new efficiency methods, its initial capital cost would likely exceed the budgeted $214-million.

The company was evaluating, besides others, an increase in throughput at an average rate higher than the originally specified 1 250 t/d rate to boost output.

Management planned to evaluate financing alternatives upon the completion of the studies to mitigate any potential increase in the project’s capital cost.

"Our objective is to optimise the Phoenix gold project and [we] have made senior management changes to strengthen our project team," Rubicon president and CEO Mike Lalonde said in a statement.

Rubicon planned to complete and release the summary of its updated mineral resource at the end of the first quarter and the report would include data from over 100 000 m of core drilling, he added.

Meanwhile, the company said it continued to make good progress with the sinking of the shaft, having reached 610 m below surface. Contractor crews were currently excavating the 610 m level station.

Shaft sinking continued, with the company expecting improved development rates.

Further, the mill carbon-in-leach building foundation and erection of the steel framework had been completed, with construction of the remaining mill building foundation continuing and due for completion in the latter part of 2014.

As of December 31, Rubicon had some $171-million in cash, cash equivalents and investments, as well as about $157-million in working capital.

Around $85-million had been spent on the project to date.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 
Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
23rd April 2025
Martin Creamer talks about safety, ruthenium and a new palladium centre plan.
On-The-Air (18/04/2025)
19th April 2025 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.142 0.435s - 145pq - 2rq
Subscribe Now