Pioneering vent shaft at Palabora holes out safely at 1200 metres
Leading underground mining contractor, Murray & Roberts Cementation and its client Palabora Mining Company celebrated the last blast at the new ventilation shaft at the mine
Murray & Roberts Cementation successfully completed the sinking of the 8.5 metre diameter vent shaft at PMC with an impeccable safety record
Aiden Schoonbee, Snr Project Manager UG Construction, Concentrator & Vent Shaft at Palabora Mining Company
Sechaba Letaba, Package Manager Vertical Dev at Palabora Mining Company
Reaching a final depth of 1,200 metres on 9 January 2024, the new ventilation shaft sunk by Murray & Roberts Cementation at Palabora Mining Company is a triumph in many respects
This article has been supplied.
Leading underground mining contractor Murray & Roberts Cementation and its client Palabora Mining Company (PMC) celebrated the last blast at the new ventilation shaft, which took its depth to a final 1,200 metres below surface on 9 January 2024.
The 8.5 metre diameter upcast vent shaft – which holed through to an already developed return air way at depth – is vital to PMC’s Lift II project. Lift II will develop access to ore resources sufficient to extend the life of this copper mine beyond 2040. Murray & Roberts Cementation Senior Project Manager Fred Durand says a key achievement was the project’s fatality free record, earned over more than a million hours worked.
“The achievement of a million fatality free hours – reached in November 2023 – is more than just a number,” says Durand. “It reflects the deep-rooted safety culture that has permeated every aspect of the project.”
The innovative sinking methods, used for the first time in South Africa, were also carefully focused on achieving zero harm. Murray & Roberts Cementation employed its Canadian shaft sinking methodology, adapted to what became called ‘the PMC way’. This method included an innovative solution to poor ground conditions, where the sidewall of the shaft was closed up within 48 hours by means of the shaft concrete lining after every three metres of advance.
“Among the improvements that this facilitated was the removal of the hazardous work by rock drill operators at the shaft bottom, who would traditionally have to install temporary support,” he explains. “We also decided not to conduct concurrent work in the shaft, so there was no risk of danger to anyone below when work was carried out from the stage.”
He emphasises the close collaboration between Murray & Roberts Cementation and PMC to ensure the success and safety of the shaft sinking. The project was significant insofar as there were many lessons learnt which could be taken forward into future projects, he says, further improving the safety record of shaft sinking practice.
“We are already looking ahead to two more important shaft sinking projects within the South African mining sector, where there is potential for certain of these learnings to be applied,” says Durand. A veteran of over 15 shaft sinking projects around Africa during his career, he admits finding aspects of the PMC way initially quite unusual when he joined the project in 2022.
“Ultimately, though, we all want to deliver safe projects, so there are many brilliant ideas that we have proven on this project,” he says. “These strategies have been combined with the company’s leading mining and engineering expertise, and made us very excited about the future of shaft sinking and contract mining.”
To facilitate streamlined programming on the project, the work ran on continuous operations with two 12 hour shifts. He notes that this improves on the usual eight hour shift system, which requires three shift changes – each change taking up valuable project time. The two-shift system requires only a morning and evening change.
The vent shaft will replace the two existing vent shafts from the Lift I project, which are likely to be affected as they are in the Lift I zone of influence. In the final stages of the project, Murray & Roberts Cementation will strip out its services from the shaft, lift out the stage and dismantle the headgear. Final demobilisation of the company’s infrastructure will be carried out during the first quarter of 2024, says Durand.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation