Pumpkin Hollow copper project, US – update


Photo by Nevada Copper
Name of the Project
Pumpkin Hollow copper project.
Location
Near Yerington, Nevada, in the US.
Project Owner/s
Nevada Copper.
Project Description
A technical report has described the Pumpkin Hollow property and its advancement, based on a phased development approach of the underground and openpit deposits, as standalone projects.
The prefeasibility study (PFS) proposes the development of the openpit project independently from the underground mine currently under construction.
The openpit study envisages a phased operation with an initial mining rate of 37 000 t/d (years 1 to 6) and expanding to 70 000 t/d (years 7 to 9). Peak production is forecast at 111 000 t/y or 244-million pounds a year.
The proposed openpit project plan includes additional drilling in areas that have mineralisation open within the pit boundary, which are currently inferred resources, as well as areas where the boundary of mineralisation remains open. The openpit has been designed to be a conventional truck-and-shovel operation, with a combination of hydraulic and electric cable shovels and haul trucks.
The openpit has a mine life of 19 years.
Processing will be undertaken through a conventional flotation concentration plant and will comprise crushing and grinding circuits, followed by a flotation process to recover and upgrade copper, gold and silver from the feed material.
The 5 000 t/d underground project will produce about 60-million pounds of copper in the first five years of operations, as well as 9 000 oz of gold and 173 000 oz of silver.
Over the underground project’s 13.5-year mine life, it will average 50-million pounds of copper a year, 8 000 oz/y of gold and 15 000 oz/y of silver.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The openpit operation has an estimated pretax net present value (NPV), at a 7.5% discount rate, of $1.04-billion and an internal rate of return (IRR) of 23%, with a payback of 4.5 years. Together, the underground and openpit operations have a pretax NPV, at a 7.5% discount rate, of $1.32-million and an IRR of 24%.
Capital Expenditure
Initial capital expenditure for the openpit is estimated at $627-million.
Planned Start/End Date
The timing of the openpit construction and operations remains flexible.
Latest Developments
Nevada Copper has suspended most mining activities at its Pumpkin Hollow underground mine and has warned that it is in default of its obligations under certain financing and contractual arrangements.
The company, which previously warned of its liquidity challenges, has not made payments, owing to certain creditors and vendors, including its mining contractor and working capital provider.
It has been seeking to raise additional funds to continue operations and is in discussions with its financing partners and third parties.
Nevada Copper has drawn $11.5-million of its previously disclosed $20-million promissory notes from shareholder Pala Investments. Further draws are subject to agreed use of proceeds and satisfactory arrangements being reached with certain creditors and vendors.
An unidentified weak rock structure was encountered at Pumpkin Hollow in the main ramp to the East South zone in early June, restricting access to the planned East South stoping zones. The company has continued the development of its priority, heading through the dike structure and into the East North mining zone, which is expected to have significantly higher copper grades and better geotechnical conditions, compared with those of the East South zone.
Although almost complete, additional work is required to finish the dike crossing.
As a result of the liquidity issues, Nevada Copper might not be able to undertake further work on the ramp to the East South zone or the dike crossing.
Key Contracts, Suppliers and Consultants
Golder Associates, Sedgman and Tetra Tech Inc (openpit PFS and technical report); and Redpath USA (mining contractor).
Contact Details for Project Information
Nevada Copper Corp, email info@nevadacopper.com.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation