Star-Orion South diamond project, Canada

13th March 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Star-Orion South diamond project.

Location
The project is situated in the Fort à la Corne diamond district of central Saskatchewan, Canada.

Project Owner/s
Star Diamond Corp.

Project Description
A preliminary economic assessment (PEA) has determined that an estimated 66-million carats of diamonds could be recovered from a surface mine over a 34-year life-of-mine.

The PEA envisages the development of two openpits, initially Orion South, followed by Star, using conventional openpit methods.

Conventional hydraulic excavators and haul trucks create a starting “key” for three bucket wheel excavators to remove the sand and clay overburden from the kimberlite. Conveyor belts will transfer the sand and clay from the excavators to the nearby overburden waste area. The exposed kimberlite will be lightly blasted and conventional hydraulic shovels will load the rock into trucks. These trucks will transfer the rock to an in-pit feeder and the kimberlite will be delivered to the processing plant using a conveyor belt.

The processing facility will have the capacity to process 45 000 t/d of kimberlite using autogenous milling, followed by screening, X-ray transmission diamond recovery and dense-media separation of heavy mineral concentrate.

The recovery section will use X-ray technology, with grease as the scavenging technology to recover the low-luminescence diamonds. The diamonds will be sorted into parcels in the on-site sorting facility.

Potential Job Creation
Not stated.

All-in Sustaining Costs/All-in Costs
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 7% discount rate, of $2-billion and an internal rate of return of 19%, with a payback of 3.5 years after the start of construction.

Capital Expenditure
Preproduction capital expenditure is estimated $1.41-billion.

Planned Start /End Date
Not stated.

Latest Developments
Star Diamond has started legal proceedings against Rio Tinto Exploration Canada (RTEC) to protect its interest in the Star-Orion South project.

Star Diamond last month flagged possible legal action over RTEC’s purported exercise in November 2019 of its four options under the option and joint venture agreement of June 2017, claiming that it did not comply with the terms of the agreement.

Exercising the four options would give RTEC a 60% interest in the Star-Orion project.

Key Contracts and Suppliers
SGS Canada, DRA Americas and ENGCOMP Engineering and Computing Professionals (PEA).

Contact Details for Project Information
Star Diamond Corp, tel +1 306 664 2202 or email stardiamondcorp@stardiamondcorp.com.

Edited by Creamer Media Reporter

Comments

 

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
Alcohol Breathalysers
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (14/03/2025)
14th March 2025 By: Martin Creamer
Magazine round up | 14 March 2025
Magazine round up | 14 March 2025
14th March 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.102 0.236s - 128pq - 2rq
Subscribe Now