SANTIAGO - Production at Capstone Copper's Mantoverde copper and gold mine in northern Chile is largely halted after the mine's desalination plant was shut down amid a nearly three-week labor strike, the company and the mine's largest union said on Thursday.
The union said production been halted, but the company said later that oxide production continued but was likely to stop soon.
A group of striking workers took over the desalination plant that provides water for the mine, the union said, adding that it had not sanctioned the plant's takeover.
Capstone in a statement on Thursday said the takeover had begun on Sunday evening, when individuals entered the desalination plant, 40 km (25 miles) from the mine, and interfered with the plant's electrical system, leading to a disruption of the water supply to Mantoverde.
Striking union members are currently preventing access and restart of operations at the desalination plant, Capstone said, adding it was seeking judicial support to regain access to the plant.
The company noted that on-site water reserves at Mantoverde were being used for essential services.
Sulphide operations were temporarily halted, while oxide operations were expected to continue until tomorrow. At that point they will also be suspended unless the water supply is restored, Capstone said.
The strike began on Friday after Union No. 2, the mine's largest, and Capstone failed to reach a collective bargaining agreement. The union, which represents some 645 members, said on January 7 that it expected a lengthy strike.
Mantoverde is 70% owned by Capstone and 30% by Mitsubishi Materials. The mine was forecast to produce between 29 000 and 32 000 metric tons of copper cathodes in 2025.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation