Taseko forecasts copper growth in 2025

The Gibraltar mine in British Columbia

The Gibraltar mine in British Columbia

20th February 2025

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Vancouver-based Taseko Mines has outlined a strong growth trajectory for its copper production in 2025, following a challenging 2024 impacted by labour disruptions and maintenance shutdowns.

The miner, which operates the Gibraltar mine in British Columbia, produced 106-million pounds of copper, which was in line with its revised guidance.

However, higher-than-normal scheduled downtime across both concentrators and an 18-day labour strike resulted in an estimated production shortfall of 15-million pounds of copper. Copper grades for the year averaged 0.23%, with total operating costs (C1) reported at $2.66/lb produced.

Looking ahead, Taseko expects copper output to climb to between 120-million and 130-million pounds in 2025 as mill operating time normalises. Further, the planned restart of the solvent extraction and electrowinning (SX/EW) plant is set to enhance production capacity.

The company said output would be weighted toward the second half of the year, with first-quarter production expected to be the lowest as lower-grade ore stockpiles are processed alongside mined material from a new pushback in the Connector pit.

“We had a strong finish to the year at Gibraltar and, with both concentrators operating well, the mine achieved a new record for quarterly mill throughput. With stable milling operations expected in 2025 we expect a significant improvement in annual production of copper and molybdenum, although we will see lower head grades in the first part of the year during a new pushback in the Connector pit. The refurbishment of the SX/EW plant is progressing on schedule and first cathode production at Gibraltar is anticipated in the second quarter," said president and CEO Stuart McDonald.

Meanwhile, Taseko also continues to advance development projects, including the Florence Copper project in Arizona. "Four drill rigs are advancing wellfield drilling which is scheduled for completion in the second quarter. Our construction workforce is currently at approximately 360 workers, and will reach peak manpower levels this quarter. First copper production continues to be targeted before the end of the year," reported McDonald.

Financially, Taseko remains well-positioned, ending the year with a cash balance of $173-million and total available liquidity of about $331-million, including its undrawn credit facility. The company is benefiting from rising copper prices, which have increased 8% since the start of the year, as well as favourable foreign exchange rates and improved cost structures at Gibraltar.

Taseko reported adjusted earnings before interest, taxes, depreciation and amortisation of $224-million and earnings from mining operations before depletion, amortisation, and non-recurring items totalling $244-million. The company recorded revenues of $608-million from the sale of 108-million pounds of copper and 1.4-million pounds of molybdenum. However, a net loss of $13-million ($0.05 loss a share) was recorded for the year, while adjusted net income stood at $57-million ($0.19 a share).

 

Edited by Creamer Media Reporter

Comments

Showroom

RioCarb
Rio-Carb

Introducing the Rio-Carb Smart Chute Concept - a revolutionary advancement in materials handling, designed for the toughest industries like mining...

VISIT SHOWROOM 
Tractor & Grader Supplies
Tractor & Grader Supplies

Tractor & Grader Supplies (TGS™): Your Trusted, Genuine Source for New Replacement Parts for Earthmoving, Construction and Mining Machinery

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 21 February 2025
Magazine round up | 21 February 2025
21st February 2025
BOLSTERING PRESENCE
The project is set to bolster Namibia’s position as one of the world’s leading uranium producers
Uranium mine moving closer to production
21st February 2025 By: Simone Liedtke

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.051 0.124s - 132pq - 2rq
Subscribe Now