Tomingley has ‘big future ahead’, says Alkane MD
The Tomingley gold operation, near Dubbo in New South Wales, is set to increase production to more than 100 000 oz/y by 2027, says ASX-listed Alkane Resources.
The company on Monday announced a five-year plan for Tomingley, which will produce 455 000 oz to 505 000 oz of gold over that period.
“Tomingley has a big future ahead of it,” said MD Nic Earner. “Our five-year plant details the capital programme that develops the opencut operations, expands the plant and moves the operation to deliver above 100 000 oz of gold a year,” he said.
When the mine was commissioned in 2014, Tomingley was based on four opencut gold deposits. The mine extended underground in 2018, currently producing exclusively from underground operations. The most recent underground development was the Roswell deposit, which started producing gold earlier this month.
With the development of the Roswell underground deposit, the next five years will see the development of the already approved opencut operations at San Antonio. This requires the relocation of a section of the Newell highway and generates sufficient ore to justify the upgrade of the Tomingley process plant to increase throughput to a nominal 1.5-million tonnes a year rate.
To access the San Antonio deposit, which is located underneath the current Newell highway, Alkane will build a new section of highway to bypass the development. The Kyalite road also needs to be realigned as it runs through the proposed opencut. These construction projects are expected to take six to nine months and must be completed before opencut development can commence.
About A$89-million in capital will be required for the highway relocation and the expansion, in addition to the current capital expenditure of about A$43-million. A final investment decision will be made early in the 2025 calendar year.
When the new openpit comes into production in 2027, production will increase to between 100 000 oz and 110 000 oz and all-in sustaining costs (AISC) will be lowered to between A$1 900/oz and A$2 100/oz.
This compares with production of 55 000 oz to 58 000 oz at an AISC of $2 150/oz to A$2 350/oz this year.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation