https://newsletter.mw.creamermedia.com
Africa|Construction|Engineering|Mining|PROJECT|Projects|Resources|Road|Services|System|Water
Africa|Construction|Engineering|Mining|PROJECT|Projects|Resources|Road|Services|System|Water
africa|construction|engineering|mining|project|projects|resources|road|services|system|water

Tumas uranium project, Namibia – update

Location map of the Tumas uranium project deposits

Photo by Deep Yellow

5th July 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Tumas uranium project.

Location
The Tumas palaeochannel system is located within Deep Yellow’s 100%-owned Reptile project, in Namibia.

Project Owner/s
Deep Yellow.

Project Description
The objective of the project is to develop a facility to treat ore from the Tumas 1, Tumas 2, Tumas 3, Tumas 1 East and Tubas ore resources.

Envisaged is an operation treating 4.15-million tonnes a year to produce up to 3.6-million pounds of uranium and 1.15-million pounds of vanadium by-product a year over a projected mine life of 22.25 years, based on existing ore reserves.

Additional resources will likely increase the life-of-mine to more than 30 years.

The mine will be a conventional, shallow opencut truck-and-shovel operation using contract mining.

The process route comprises a beneficiation process to reject barren material, leaching, solid liquid separation, pregnant leach solution concentration, vanadium recovery, uranium recovery and uranium barren liquor treatment.

The project also includes the construction of a 13.5 km site access road, a 45.1 km 132 kV powerline and a 65 km water supply pipeline.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
A definitive feasibility study (DFS) review completed in December 2023 found that the base case uranium price had increased from $65/lb to $75/lb, owing to market-strengthening conditions, which resulted in a post-tax net present value (NPV) increase of the project by 68% to $570-million, or A$838-million, with an internal rate of return (IRR) of 27%.

In a more optimal scenario of the uranium price reaching $90/lb, the project’s NPV increases to $878-million and its IRR to 36.1%.

Capital Expenditure
The DFS review has validated a lower initial capital cost for Tumas of $360-million, or A$529-million, down 64% from the initial estimates in the DFS.

Recosting work has identified further potential gains to be made during the detailed engineering phase of the project, with more gains to be made across beneficiation, washing and concentration as demonstrated by metallurgical testwork not having been incorporated into the recosting effort.

Planned Start/End Date
Production startup is expected in 2026.

Latest Developments
Deep Yellow has appointed Nedbank as the mandated lead arranger and bookrunner to coordinate and arrange financing for the project.

The bank has an extensive track record in financing mining projects across Africa.

The proposed project financing is expected to deliver a competitively priced cost of funding for project development. The project finance process will run in junction with the detailed engineering under way. The final investment decision is expected before the end of the year.

“It is pleasing that our schedule is holding for production startup during third quarter of the 2026 calendar year,” MD and CEO John Borshoff has said.

Key Contracts, Suppliers and Consultants
Ausenco Services (DFS and engineering, procurement and construction management).

Contact Details for Project Information
Deep Yellow, tel +61 8 9286 6999 or email info@deepyellow.com.au.
 

Edited by Creamer Media Reporter

Comments

 

Showroom

VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Minerals Council South Africa CEO Mzila Mthenjane
Minerals Council optimistic about ongoing MPRDA review
13th December 2024 By: Marleny Arnoldi
Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.118 0.253s - 127pq - 2rq
Subscribe Now