Americas Gold and Silver tracking towards upper end of guidance; ups Galena hoist capex
North American precious metals producer Americas Gold and Silver expects its 2022 production to be at the upper-end of its guidance of 4.8-million to 5.2-million silver-equivalent ounces and says its production will rise to between 7-million and 7.4-million ounces in 2024.
“The company anticipates a strong finish to the year in the fourth quarter with silver-equivalent production to meet or exceed the upper-end of the guidance range,” president and CEO Darren Blasutti said on Thursday.
Announcing third-quarter production results, Americas reported consolidated attributable production of 331 000 oz of silver and 1.34-million silver-equivalent ounces. Silver production increased by 92% year-on-year and increased 11% quarter-on-quarter.
Silver production is expected to increase further in the fourth quarter, as output ramps up into the higher silver grade Upper Zone of the San Rafael deposit at the Cosala Operations and the Galena Complex exploits higher silver grade stopes.
“The completion of the Galena hoist is expected to add operational flexibility and significantly increase production at the Galena Complex moving forward. As a result, the company increased its convertible debt subsequent to quarter-end to ensure that the Galena hoist project remains fully funded and on schedule,” said Blasutti.
Americas has increased the estimated capital cost of the Galena hoist project by $2.2-million to $8.9-million, with about half of the increase owing to higher installation costs. Despite the inflationary pressures at the hoist project, overall capital at the Galena complex is expected to be within 6% of the original budget of $20-million for 2022.
The company amended its existing RoyCap Convertible Debenture by increasing the principal balance by C$7-million to a total outstanding principal of C$19-million subsequent to quarter end. In addition, the parties agreed to amend the interest rate to a fixed rate of 9.5% a year, the conversion price to C$1.00 a share, and retraction option terms.
Commissioning of the Galena hoist will start in December.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation