https://newsletter.mw.creamermedia.com
Construction|Contractor|Electrical|Gold|Mining|PROJECT|Drilling|Operations
Construction|Contractor|Electrical|Gold|Mining|PROJECT|Drilling|Operations
construction|contractor|electrical|gold|mining|project|drilling|operations

Calibre’s Valentine project’s costs rise, FY guidance downgraded

21st October 2024

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Construction of the multimillion-ounce Valentine gold mine, in Newfoundland and Labrador, is progressing well, reaching nearly 81% completion by the end of last month, TSX-listed Calibre Mining president and CEO Darren Hall reported on Friday.

However, he also said that cost pressures had emerged, mainly owing to contractor performance, resulting in increased manpower and associated costs.

While the performance issues had been addressed, Calibre stated that the Valentine project’s estimated initial project capital was now forecast to be about C$744-million, compared with a C$653-million estimate in August.

Hall stressed, however, that the project remained fully funded and that Calibre was “confidently tracking” towards mechanical and electrical completion early in the first quarter of 2025.

“With approximately C$300-million in cash and C$197-million cost to complete, the Valentine build remains fully funded and on track for first gold during the second quarter of 2025, representing a significant milestone in Calibre’s strategy to diversify and grow its production in Canada,” he said.

Meanwhile, Calibre lowered its full-year guidance owing to lower-than-expected third-quarter performance of 46 076 oz, comprising 36 427 oz from its Nicaragua operations and 9 639 oz from Nevada, US.

Hall explained that the Nicaragua production fell short of targets because of higher-than-expected historical artisanal mining activity on the initial benches of the Volcan openpit and mine sequencing at Limon.

The consolidated 2024 production guidance had revised to between 230 000 oz and 240 000 oz, from an original guidance of 275 000 oz to 300 000 oz.

Hall stated that ore tonnes and grade from Volcan were now aligning with expectations and the deposit model had been confirmed by infill drilling. Consolidated fourth-quarter gold production is expected to be 70 000 oz to 80 000 oz, driven by Nicaragua’s fourth-quarter mine plans, which indicated significantly higher ore tonnes mined.

Hall said that it expected to build a stockpile of about 30 000 oz at Libertad, which would be processed in 2025.

“We are guiding to finish 2024 approximately 18% below the midpoint of our original production guidance, the 30 000 oz stockpile positions us well for a strong close to the year and a solid start to 2025,” said Hall.

Edited by Creamer Media Reporter

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.094 0.197s - 129pq - 2rq
Subscribe Now