https://newsletter.mw.creamermedia.com
Contractor|Environment|Financial|Gold|Installation|Mining|Power|PROJECT|Projects|Solar|Steel|Storage|Underground|Waste|Drilling|Waste|Operations
Contractor|Environment|Financial|Gold|Installation|Mining|Power|PROJECT|Projects|Solar|Steel|Storage|Underground|Waste|Drilling|Waste|Operations
contractor|environment|financial|gold|installation|mining|power|project|projects|solar|steel|storage|underground|waste-company|drilling|waste|operations

Centamin reports increased production at Sukari

20th July 2022

By: Darren Parker

Creamer Media Senior Contributing Editor Online

     

Font size: - +

LSE- and TSX-listed Centamin delivered increased gold production of 110 788 oz at its flagship Sukari gold mine, in Egypt, for the second quarter, which represents an 11% year-on-year and a 19% quarter-on-quarter increase.

The company said on July 20 that this production increase was attributable to the successful transition to owner mining, alongside ongoing productivity improvements such as the use of lightweight high-capacity truck trays in the openpit.

Sukari is Egypt’s largest and first modern gold mine, and is one of the largest producing gold mines globally. Since production began in 2009, it has produced about five-million ounces of gold.

“Sukari delivered the planned increase in production during [the second quarter] and we remain on track to meet full-year production and cost guidance.

“[It] was the first full quarter of underground owner operations at Sukari following the transition from contractor operations during [the first quarter] and the Sukari team delivered significant improvements in both productivity and costs,” Centamin CEO Martin Horgan said.

Total material moved increased by 30% year-on-year to 33.4-million tonnes, resulting from improved operating efficiencies and productivity, and included the contractor waste stripping programme.

Openpit ore mining activity continued to focus primarily on the Stage 5 North area during the quarter under review, with ore contributions from Stage 4. The openpit ore mined during the quarter had an average mined grade of 1.07 g/t of gold, which was a 41% improvement over the previous year, driven by ore from Stage 4 and improved grades with depth from the primary mining area of Stage 5 North.

Meanwhile, the second quarter represented the first full quarter of owner mining operations in the underground section, which delivered a significant improvement in productivity relative to recent performance, the company said.

As a result of this, volumes increased and grades improved as mining activities progressed into higher-grade areas. Centamin said it expected to see further improvements in the underground performance as it continued to optimise operations, in parallel with the underground expansion study, which is planned to be finalised in the third quarter.

Additionally, Centamin spent $67.3-million on key capital projects during the quarter, including a 36 MW off-grid solar plant and 7.5 MW battery storage project, as well as underground development and paste fill plant.

The solar power project activities completed in the period included the continued drilling and installation of tracker posts, as well as ongoing installation of solar modules, with more than 80% installed.

Centamin said its solar project was on track for commissioning during the third quarter.

The paste fill plant civil works were also completed and structural steel works were well advanced, the company reported.

“Continued progress was made at our key projects and we remain focussed on cost control across all our operations with a number of initiatives targeting completion in [the second half of the year] that are expected to partially offset the current inflationary environment,” Horgan said.

Horgan said the company would release its detailed interim financial results and would declare an interim dividend on August 4.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Alcohol Breathalysers
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 
Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.253 0.437s - 129pq - 2rq
Subscribe Now