Doropo gold project, Côte d'Ivoire

Image of Doropo map

Photo by Resolute Mining

27th February 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Doropo gold project.

Location
Bounkani region, in north-eastern Côte d’Ivoire, about 480 km north-east of Abidjan and roughly 50 km north of Bouna, near the border with Burkina Faso.

Project Owner/s
Resolute Mining Limited, through its wholly owned Ivorian subsidiaries Ampella Mining Côte d’Ivoire and Ampella Mining Exploration Côte d’Ivoire.

Project Description
The Doropo gold project is a large-scale, openpit gold development underpinned by a definitive feasibility study (DFS) update completed in December 2025. The project comprises 11 defined deposits, of which seven are included in the current mine plan, clustered around a central processing hub with several satellite pits. 

Conventional drill-and-blast, load-and-haul openpit methods will be used to mine, with all production mining activities performed by a contract mining operator. 

Ore from the hub pits will be delivered directly to the processing plant, while material from satellite deposits will be stockpiled and rehandled for transport to the plant. 

Waste rock will be placed in engineered waste rock dumps, with progressive rehabilitation planned throughout the life-of-mine (LoM). 

The processing facility is designed for a throughput of 4.9-million tonnes a year over an estimated 13-year mine life, and will use a gravity and carbon-in-leach flowsheet. 

Average life-of-mine metallurgical recoveries are estimated at about 88%, supporting average annual gold production of about 169 000 oz and total production of about 2.2-million ounces over the LoM. 

The project requires the development of extensive greenfield infrastructure, including a 90 kV grid power connection from the Bouna substation, a tailings storage facility, water harvesting and storage dams, site access roads, nonprocess infrastructure and an accommodation village. 

Resolute will retain owner-managed technical, operational and support functions.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Based on a long-term gold price of $3 000/oz and a 5% discount rate, the project delivers a pretax net present value (NPV) of $1.96-billion and an internal rate of return (IRR) of 57%. 

On an after-tax basis, the NPV is estimated at $1.46-billion, with an IRR of about 49%. The payback period from first production is estimated at about 1.7 years.

Capital Expenditure
Initial capital expenditure is estimated at $516-million.

Planned Start/End Date
Subject to a final investment decision, construction and early works are expected to start ahead of first gold production targeted from 2027. 

The current mine plan supports an estimated operating life of about 13 years from the start of production.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
Lycopodium Minerals (engineering, procurement and construction management and DFS update); Orelogy Mine Consulting (mining studies); Knight Piésold (tailings, water and infrastructure); ECG Engineering (high-voltage power supply); and The Mineral Corporation (due diligence).

Contact Details for Project Information
Resolute Mining, tel +61 8 9261 6100 or email contact@rml.com.au.
 

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

ACTOM
ACTOM

Your one-stop global energy-solution partner

VISIT SHOWROOM 
ATI Systems
ATI Systems

ATI systems comprises five divisions: electrical assemblies, drives and controls, feedback sensors, enclosures, and strip guiding.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
24th February 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.056 0.152s - 104pq - 2rq
Subscribe Now