https://newsletter.mw.creamermedia.com

Doropo gold project, Côte d'Ivoire – update

Image of gold nuggets

13th February 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Doropo gold project.

Location
Bounkani region, in north-eastern Côte d’Ivoire, about 480 km north-east of Abidjan and roughly 50 km north of Bouna, near the border with Burkina Faso. 

Project Owner/s
Resolute Mining Limited, through its wholly owned Ivorian subsidiaries Ampella Mining Côte d’Ivoire and Ampella Mining Exploration Côte d’Ivoire. 

Project Description
The Doropo gold project is a large-scale, openpit gold development underpinned by a definitive feasibility study (DFS) update completed in December 2025. The project comprises 11 defined deposits, of which seven are included in the current mine plan, clustered around a central processing hub with several satellite pits.

Conventional drill-and-blast, load-and-haul openpit methods will be used to mine, with all production mining activities performed by a contract mining operator. 

Ore from the hub pits will be delivered directly to the processing plant, while material from satellite deposits will be stockpiled and rehandled for transport to the plant. Waste rock will be placed in engineered waste rock dumps, with progressive rehabilitation planned throughout the life-of-mine (LoM).

The processing facility is designed for a throughput of 4.9-million tonnes a year over an estimated 13-year mine life, and will use a gravity and carbon-in-leach flowsheet. 

Average life-of-mine metallurgical recoveries are estimated at about 88%, supporting average annual gold production of about 169 000 oz and total production of about 2.2-million ounces over the LoM.

The project requires the development of extensive greenfield infrastructure, including a 90 kV grid power connection from the Bouna substation, a tailings storage facility, water harvesting and storage dams, site access roads, nonprocess infrastructure and an accommodation village. 

Resolute will retain owner-managed technical, operational and support functions.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Based on a long-term gold price of $3 000/oz and a 5% discount rate, the project delivers a pretax net present value (NPV) of $1.96-billion and an internal rate of return (IRR) of 57%. On an after-tax basis, the NPV is estimated at $1.46-billion, with an IRR of about 49%. The payback period from first production is estimated at about 1.7 years.

Capital Expenditure
Initial capital expenditure is estimated at $516-million. 

Planned Start/End Date
Subject to a final investment decision, construction and early works are expected to start ahead of first gold production targeted from 2027. The current mine plan supports an estimated operating life of about 13 years from the start of production.

Latest Developments
The Côte d'Ivoire Council of Ministers has officially announced the award of a 14-year mining right for Resolute Mining's Doropo gold project, paving the way for the company to increase its yearly gold production above 500 000 oz by the end of 2028.

The award of the mining permit is the final governmental approval required to launch the development and operation of the gold project, with the official Presidential Decree expected in the weeks following the Council of Ministers’ meeting. Resolute expects to make a final investment decision on the project soon.

Key Contracts, Suppliers and Consultants
Lycopodium Minerals engineering, procurement and construction management and DFS update); Orelogy Mine Consulting (mining studies); Knight Piésold (tailings, water and infrastructure); ECG Engineering (high-voltage power supply); and The Mineral Corporation (due diligence). 

Contact Details for Project Information
Resolute Mining, tel +61 8 9261 6100 or email contact@rml.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 
Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Debswana Diamond Company COO Koolatotse Koolatotse
Debswana highlights partnerships and diversification drive beyond diamond
12th February 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.322 0.405s - 127pq - 2rq
Subscribe Now