Name of the Project
Eland mine complex.
Location
South-eastern portion of the western limb of the Bushveld Complex, near Brits, in South Africa’s North West province.
Project Owner/s
Northam Platinum Holdings Limited.
Project Description
Northam acquired the Eland mine from Glencore for R175-million in 2017.
The Eland mine had been on care and maintenance since 2015. Operations were restarted in 2019, following the conclusion of a feasibility study on the Kukama project, particularly the western decline system and mining section of Eland upper group two (UG2) mine.
The operations comprised the development of the underground mine on a hybrid array of conventional breast stoping and mechanised ore transport using hydropower technology imported from Northam’s Zondereinde mine.
Eland hosts a shallow, UG2 orebody containing 14.4-million ounces of platinum, palladium, rhodium and gold, or 4E, resources and 3.2-million ounces of mineral reserves. Mineral resources and reserves include those contained within the Maroelabult mine, which was acquired from Barplats Mines in 2020.
Maroelabult is situated immediately west of Eland, and underground development from the Kukama decline has connected with that of the Maroelabult decline, which is aiding the provision of underground services, as well as the build-up of mineable reserve.
The inclusion of Maroelabult will enhance Eland mine’s ramp-up, which will produce 180 000 oz/y 4E in concentrate at steady state by 2028.
Potential Job Creation
Eland currently employs 2 200 people. At steady state in 2028, the mine will provide direct, long-term employment for more than 2 500 people.
Net Present Value/Internal Rate of Return
Not stated.
Capital Expenditure
Total capital expenditure is estimated to reach R4.5-billion by 2028. R2.7-billion has been spent to date.
Planned Start/End Date
Mine development started in 2020. Production is forecast to reach 100 000 oz/y of 4E in the 2025 financial year and will increase to a steady state of 180 000 oz/y by the 2028 financial year.
Latest developments
The development of an underground connection between Maroelabult and Kukama has been concluded, as well as the development of both decline systems. This has enhanced the provision of underground services, as well as the build-up of mineable reserve.
To date, the decline systems have been advanced more than 2 500 m, which is on plan, and have accessed eight strike drives – Northam requires 11 strike drives for steady-state production.
In the year to June 30, 2023, stoping of UG2 reef continued in the upper western portion of the mine. More than 25 800 m2 of stoping to date have allowed for the optimisation of in-stope practices, as well as ore-handling systems.
Lateral development has started at the Nyala section to effect limited mining in the medium term.
Batch treatment of run-of-mine (RoM) ore sources is ongoing, together with third-party surface material and the retreatment of tailings from the Eland TSF.
Concentrator recoveries for RoM ore are in line with expectations, and volumes will increase as ramp-up continues to steady state.
Key Contracts, Suppliers and Consultants
None stated.
Contact Details for Project Information
R&A Strategic Communications, on behalf of Northam Platinum, tel +27 11 880 3924 or email northam@rasc.co.za.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation