https://newsletter.mw.creamermedia.com
Africa|Construction|Financial|Gold|Infrastructure|Pipelines|PROJECT|Roads|Slurry|Storage|Surface|Underground|Water|Environmental|Infrastructure|Operations
Africa|Construction|Financial|Gold|Infrastructure|Pipelines|PROJECT|Roads|Slurry|Storage|Surface|Underground|Water|Environmental|Infrastructure|Operations
africa|construction|financial|gold|infrastructure|pipelines|project|roads|slurry|storage|surface|underground|water|environmental|infrastructure|operations

Far West Gold Recoveries operation, South Africa – update

Headgear for the FWGR project

Photo by DRDGOLD

29th August 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Far West Gold Recoveries (FWGR) operation.

Location
Gauteng, South Africa.

Project Owner/s
DRDGOLD’s acquisition of Sibanye-Stillwater’s West Rand Tailings Retreatment Project assets was finalised on July 31, 2018. Following the successful implementation of the transaction between the two companies, Sibanye owned 38.05% of the issued share capital of DRDGOLD.

Under the terms of the transaction, entered into in November 2017, Sibanye agreed to exchange selected surface-gold processing assets and tailings storage facilities (TSFs) for shares in DRDGOLD.

Sibanye-Stillwater also had an option to subscribe for further shares in DRDGOLD within 24 months at a 10% discount. In January 2020, Sibanye exercised this option, obtaining a 50.1% controlling interest in DRDGOLD.

Project Description
FWGR is a surface gold retreatment operation, which treats old slime dams in the West Rand goldfields. The operation is being rolled out in a phased approach.

Phase 1 included early-stage production, involving upgrading the Driefontein 2 plant (DP2) to process tailings from the Driefontein 5 dump at between 400 000 t and 600 000 t a month, and depositing the residue on the Driefontein 4 tailings dam, which was upgraded to a cyclone deposition dam to cater for the higher throughput.

Phase 2 envisages the construction of a high-volume central processing plant capable of processing between 1.2-million and 2.4-million tonnes a month, the continued use of DP2 at an increased 600 000 t a month, and the development of a new 800-million-tonne regional TSF (RTSF) capable of receiving up to three-million tonnes a month. 

In this phase, reclamation will initially be from the Driefontein 3, Libanon and Kloof 1 dumps, and then from the Ventersdorp North and South dumps. The scale of the infrastructure established in this phase will allow for the reclamation from other sources in the region. The objective is to clean up the regional landscape by reprocessing tailings that are currently on dolomite, and redeposit the reclaimed material onto a properly designed and managed megadam, thereby reversing the potential pollution of underground water in the region.

DP2/RTSF pipeline infrastructure includes a 135 km pipeline comprising a slurry pipeline, two residue pipelines and a return water pipeline linking the plant and the RTSF. 

As an alternative to Phase 2, or should Phase 2 be delayed, Phase 1 can be extended by extending deposition onto the Driefontein 4 tailings dam, owing to the good cyclone splits being achieved at the tailings dam. Envisaged is the treatment of the remaining tonnes from Driefontein 5 and then processing material from Driefontein 3.

Potential Job Creation
Since its inception, FWGR has secured employment for more than 150 employees and is committed to its environmental, social and governance mandate, as well as social upliftment programmes, in the far West Rand area of operations. With the implementation of Phase 2 and the extended life-of-mine (LoM), more opportunities are expected to result from DRDGOLD’s value creation activities.

Capital Expenditure
DRDGOLD invested R330-million of capital in Phase 1.

DRDGOLD reported in August 2024 that it anticipated capital investment of about R7-billion at FWGR over the next five years.

Planned Start/End Date
Phase 1 commercial production started within eight months of the acquisition, on April 1, 2019, and made its maiden full 12-month contribution to DRDGOLD’s financial results in the 2020 financial year.

Beneficial occupation of the RTSF is targeted for the first quarter of the 2027 financial year.

Monthly throughput capacity of 1.2-million tonnes at the DP2 is planned for the second half of the 2027 calendar year. This could potentially add 25 years to FWGR's LoM.

Latest Developments
The completion of DP2 is expected in the first quarter of the 2027 financial year. Initial feed to the expanded plant will be from the Driefontein 3 and the Libanon dumps, with 600 000 t a month from each plant.

Construction of the RTSF is progressing well, barring some delays caused by rainy weather. One-third of the RTSF is expected to be completed in the first quarter of the 2027 financial year to align with the commissioning of the DP2 plant expansion. Construction of the rest of the RTSF will continue simultaneously with the start of deposition.

Sixty kilometres of the 130 km of pipeline infrastructure at DP2/RTSF has been built. Work so far includes the successful underpassing of the N12 highway and the crossing of five provincial roads. 

Key contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
R&A Strategic Communications on behalf of DRDGOLD, Jane Kamau, tel +27 11 880 3924 or email jane@rasc.co.za.
 

Edited by Creamer Media Reporter

Comments

Showroom

Amsted Reelin image
Amsted Reelin

REELIN is Currently the largest supplier of Bearings to Transnet. We have contracts to supply bearings, draft gears slackadjusters and other...

VISIT SHOWROOM 
The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Resources Watch
Resources Watch
27th August 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.056 0.186s - 130pq - 2rq
Subscribe Now