https://newsletter.mw.creamermedia.com
Building|Construction|Copper|Electrical|Installation|Mining|Pipe|PROJECT|Service|Steel|Surface|Underground|Water|Welding|Environmental|Pipe
Building|Construction|Copper|Electrical|Installation|Mining|Pipe|PROJECT|Service|Steel|Surface|Underground|Water|Welding|Environmental|Pipe
building|construction|copper|electrical|installation|mining|pipe-company|project|service|steel|surface|underground|water|welding|environmental|pipe

Florence Copper in situ copper recovery facility, US – update

Copper production testing facility

Photo by Taseko Mines

24th January 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Florence Copper in situ copper recovery (ISCR) facility.

Location
Arizona, in the US.

Project Owner/s
Florence Copper Incorporated, a wholly owned subsidiary of midtier copper producer Taseko Mines.

Project Description
The Florence deposit contains 2.5-billion pounds of copper in 345-million tons of probable reserves.

The project proposes to build and operate the Florence Copper ISCR facility, and produce 85-million pounds a year of copper over the 22-year life-of-mine (LoM). Total LoM production is estimated at 1.5-million pounds of copper.

ISCR is an extraction method used for selected mineral deposit conditions as an alternative to openpit or underground mining methods.

ISCR extracts copper by injecting a weak sulphuric acid solution, referred to as raffinate, through targeted portions of the mineral deposit using an array of injection wells. The raffinate passes through natural fractures and voids in the deposit and dissolves the copper mineralisation.

The copper laden solution, known as pregnant leach solution (PLS), is collected in recovery wells where it is pumped to the surface for processing. Copper is extracted from the PLS using solvent extraction and electrowinning (SX/EW) techniques producing a saleable copper cathode product.

Potential Job Creation
As of January 15, 2025, about 290 construction and support personnel were on site.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 8% discount rate, of $930-million and an internal rate of return of 47%, with a payback of 2.6 years.

Capital Expenditure
The project has an initial capital expenditure of $232-million.

Planned Start /End Date
Commercial production is expected to start in 2025.

Latest Developments
The project has surpassed the halfway mark and remains on track for first production by the end of 2025.

Providing a construction update on January 15, Taseko stated that, as of December 31, overall project completion reached 56%. 

Construction activities are advancing on schedule, with nearly 450 000 project hours logged without any reportable injuries or environmental incidents. 

Key fourth-quarter milestones include the completion of process ponds and the surface water run-off pond, alongside the placement and welding of SX settler and launder modules.

Seventeen production wells were fully built during the quarter, bringing the total to 51 of the planned 90 wells.

The main pipe corridor from the wellfield to the process plant is nearly complete, and installation of high-density polyethylene piping is ongoing.

Field-erected process and service tanks are under construction, while mechanical and piping installations have progressed throughout the SX/EW. The structural steel erection for the SX pipe rack is nearing completion, with piping installation and electrical work under way.

Further, the water treatment building has been erected, and preparations are in progress for the electrowinning building.

Taseko president and CEO Stuart McDonald has said that costs remain in line with guidance.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Taseko Mines, tel +1 778 373 4533 or email investor@tasekomines.com.

Edited by Creamer Media Reporter

Comments

Latest Multimedia

Resources Watch
Resources Watch
Updated 5 hours ago

Latest News

Resources Watch
Resources Watch
Updated 5 hours ago

Showroom

Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 
The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Martin Creamer and Francisco Baudrand
Enaex Africa transforms beyond compliance
14th April 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.153 0.289s - 129pq - 2rq
Subscribe Now