Goulamina lithium project, Mali – update

Image of lithium core from the Goulamina project

18th November 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Goulamina lithium project.

Location
Southern Mali, about 50 km west of Bougouni.

Project Owner/s
Firefinch subsidiary Leo Lithium, and Chinese partner Jiangxi Ganfeng Lithium.

Project Description
An update to the October 2020 Goulamina definitive feasibility study (DFS) in December 2021 has confirmed that the project is among the world’s biggest lithium developments.

Stage 1 spodumene concentrate production is estimated at 506 000 t/y, increasing to a peak of 880 000 t/y in Stage 2. The DFS envisages a standard openpit mining operation.

The flowsheet will comprise:

• three-stage crushing to a P80 of 6.2 mm, with a fine-ore bin and overflow dead stockpile;

• closed-circuit ball milling and screening to an estimated P80 of 180 µm, based on a closing screen P100 of 212 µm;

• two-stage magnetic separation;

• three-stage flotation (roughing, cleaning and recleaning);

• concentrate dewatering, filtration and storage;

• separate flotation and process tailings thickening, with common tailings pumped to a tailings storage facility;

• reagent mixing and distribution;

• separate flotation and process water circuits; and

• air services.

The DFS update proposes the construction of a 2.3-million-tonne-a-year throughput plant, incorporating in the design the infrastructure and equipment for the construction of a Stage 2 expansion to increase plant throughput to four-million tonnes a year.

The project is expected to have a minimum mine life of 21 years, producing 15.6-million tonnes of spodumene concentrate over that period.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of $4-billion and an internal rate of return (real) of 97.8%.

Capital Expenditure
Stage 1 will cost about $255-million and Stage 2 $70-million.

A formal investment decision on Goulamina was taken in March in 2022.

Planned Start/End Date
Firefinch expects to complete construction in early 2024 and commissioning in about mid-2024, with full production expected in 2025.

Latest Developments
Leo Lithium has finalised a shipping solution for product from its Goulamina lithium project.

The company has signed an agreement with SEA-Invest for port services, including product unloading, storage and shiploading at the Abidjan port.

Under the agreement, Leo has secured warehouses with a footprint of 9 000 m2  on the wharf of the Port of Abidjan, equating to about 60 000 t of product storage. The agreement stipulates a minimum product throughput of 250 000 t/y; however, there is no upper limit on quantities that can be exported.

The agreement also includes handling unit rates and loading rates, which are in line with cost forecasting in the DFS update, Leo Lithium has said.

Key Contracts, Suppliers and Consultants
Lycopodium (updated DFS and engineering procurement and associated project management services contract).

Contact Details for Project Information
Firefinch, tel +61 8 6149 6100 or email info@firefinchltd.com.

Edited by Creamer Media Reporter

Comments

Showroom

SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 
The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.108 0.265s - 129pq - 2rq
Subscribe Now