https://newsletter.mw.creamermedia.com
Africa|Consulting|Design|Environment|Financial|Infrastructure|Mining|Power|PROJECT|Resources|Water|Maintenance|Infrastructure|Operations
Africa|Consulting|Design|Environment|Financial|Infrastructure|Mining|Power|PROJECT|Resources|Water|Maintenance|Infrastructure|Operations
africa|consulting-company|design|environment|financial|infrastructure|mining|power|project|resources|water|maintenance|infrastructure|operations

Kayelekera uranium restart project, Malawi – update

Aerial view of Kayelekera project

Photo by Lotus Resources

28th November 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Kayelekera uranium restart project.

Location
Karonga district, northern Malawi.

Project Owner/s
Advanced uranium developer Lotus Resources' 85%-owned subsidiary Lotus Africa.

Project Description
Kayelekera, currently under care and maintenance, successfully produced uranium in the past, having delivered about 11-million pounds of uranium to the market from 2009 to 2014.

An accelerated restart plan completed in October 2024 has promised positive operational and financial outcomes, assuming a long-term uranium price of $90/lb.

Under the plan, the life-of-mine (LoM) production target is estimated at 19.3-million pounds of triuranium octoxide over a ten-year mine life. Production of 2.4-million pounds of uranium is expected over the first seven years of operation.

Potential Job Creation
More than 600 jobs will be created in the local community. The project’s workforce is expected to expand as work progresses, ensuring that the mine restarts on schedule.

Net Present Value/Internal Rate of Return
The restart plan promises pretax and after-tax net present value of $439-million and $301-million, respectively, with pretax and after-tax internal rate of return of 80% and 66%, respectively. Payback should be achieved within two years.

Capital Expenditure
The October 2024 accelerated restart plan reduces initial restart capital through a phased approach by focusing on capital items essential to the restart, with the remaining capital expenditure (capex) continuing off the critical path to optimise operations and cost structure. 

As a result, the initial restart capex to first uranium production has been reduced to $50-million from $88-million.

Planned Start/End Date
In a statement issued by Lotus on October 8, 2024, it reported that the time to first uranium production had been reduced from about 15 months to between eight and ten months by phasing in the completion of nonessential site infrastructure, such as grid power and an acid plant rebuild, beyond first production.

Latest Developments
Lotus Resources has fired the first blast at the mine, marking the formal restart of openpit mining as the operation advances towards steady-state production in early 2026.

The blast is the first since Kayelekera resumed uranium production in August, and signals the shift from processing solely stockpiled ore to incorporating newly mined run-of-mine (RoM) material. Ore deliveries from the pit to the RoM pad are expected to start in the coming weeks.

Lotus is targeting steady-state output of 200 000 lb of uranium oxide a month in the first quarter of 2026.

The company has said stockpiled ore from previous mining campaigns continues to outperform grade expectations, supporting early yellowcake production. Freshly mined ore will now be blended with these stockpiles to underpin the ramp-up profile.

Product accreditation with uranium converters is also progressing, with samples delivered to all three major Western converters in the US, Canada and France.

Key Contracts, Suppliers and Consultants
Orelogy Mining Consultants (pit optimisation, mine design and production scheduling ore reserve); Gill Lane Consulting (mineral resource estimate); Merrill Ford Independent Metallurgical Operations (metallurgical/process design); Steinert (ore sorting); Nagrom (metallurgical testwork); Senet (process plant and infrastructure, and cost estimate compilation); SLR Consulting (tailings and water); Mine Technics (openpit); SLR Consulting (plant); InfinityCorp (financial model); Dhamana (community and environment); and Mine Earth (mine closure plan and cost estimate).

Contact Details for Project Information
Lotus Resources, tel +61 89 2000 3427 or email info@lotusresources.com.au.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Comments

Showroom

ECG Engineering
ECG Engineering

ECG provides specialised electrical engineering services to the Mining, Utilities, Materials Handling and Industrial industries, with extensive and...

VISIT SHOWROOM 
Rio-Carb
Rio-Carb

Rio Carb is an OEM (Original Equipment Manufacturer) of R-C700 Chromium Carbide (CrC) alloy clad wear plates and pipes used for heavy materials...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 28 November 2025
Magazine round up | 28 November 2025
28th November 2025
Thos Begbie - more than a foundry
Thos Begbie - more than a foundry
27th November 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.246 0.389s - 131pq - 2rq
Subscribe Now