Name of the Project
KFM – Phase II project.

Location
Bayeke, Lubudi, Lualaba, in the Democratic Republic of Congo.

Project Owner/s
A joint stock company incorporated in China CMOC Group.

Project Description
The project is expected to increase the project’s processing capacity of raw ore by 7.26-million tonnes and, upon reaching full production, have an expected average increase of 100 000 t/y of copper metals.

The first phase of KFM reached full capacity in 2023.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
$1.08-billion.

Planned Start/End Date
The project is expected to take two years to build and is scheduled to be completed and put into production in 2027.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
Not disclosed.

Contact Details for Project Information
CMOC Group investor liaison, tel +86 21 80330506 or email 603993@cmoc.com.


 

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 
Aluminium Federation of South Africa
Aluminium Federation of South Africa

The Aluminium Federation of South Africa (AFSA), is the voice of the South African aluminium industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Gold and platinum developments make headlines
Gold and platinum developments make headlines
27th February 2026
Magazine round up | 27 February 2026
Magazine round up | 27 February 2026
27th February 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.049 0.2s - 105pq - 2rq
Subscribe Now