Late project delivery part of Eskom’s monetary woes
LEARNING EXPERIENCE The construction of Kusile (pictured) will have the benefit of lessons learnt at Medupi
The behind-the-times and above-budget construction of State-owned power utility Eskom’s Medupi and Kusile coal power stations, both with an output of 4 800 MW, is a significant contributor to Eskom’s monetary crisis, states KPMG South Africa chairperson Ahmed Jaffer.
Eskom needs to repay long-term loans in the next two to five years, totalling about R104-billion, and Jaffer argues that, if Medupi and Kusile were fully operational by 2014 and 2017 respectively, as had been planned, the incurred debt would have been paid through normal cash from operations.
However, Medupi is expected to be on line only by 2020, with Kusile due for completion only in 2021.
Jaffer maintains that some of the large overseas contractors working at Medupi and Kusile are to blame for the late delivery of the power stations, as some of these companies had underestimated the work that needed to be done and, as a result, they did not dedicate their best skills base to the projects.
Construction on the power plants started during a busy period of power procurement worldwide because South Africa, too, does not have the capabilities to build these types of megaprojects, Eskom was at a disadvantage as the best power plant construction personnel were not being allocated to South Africa by international firms, he laments.
Jaffer admits, however, that in-house issues, such as strikes and management instability, have also curtailed the progress of the two megaprojects, but asserts that appointing CEO Brian Molefe and CFO Anoj Singh has helped to stabilise Eskom’s operations.
He also argues that Eskom has employed people with “excellent” technical capabilities, including Medupi power station project director Roman Crookes.
Crookes previously noted that several actions had been taken to transfer the lessons learnt from the much-delayed commissioning of Unit 6 at Medupi to the other five units, which will be introduced in stages from 2017 to 2020.
Unit 6 first began supplying power into the grid in March and has been producing at full capacity of 800 MW since May.
Although Jaffer says the lessons learnt at Medupi will also be transferable to Kusile, he reiterates that Eskom faces real difficulties because it does not have cost-reflective tariffs. He argues that the all-in tariff of about 70c that users pay to Eskom should be increased by up to 50% to between 95c and R1.05 to truly reflect the cost of power generation.
However, the National Energy Regulator of South Africa, having sanctioned an 8% tariff cap in June, did not allow Eskom to move towards a cost-reflective tariff as requested by the utility; government’s equity injection of R23-billion was not enough to cover the power utility’s shortfall.
The multiyear price determination revenue shortfall of R225-billion up to March 31, 2018, would seriously impact Eskom’s equity as significant losses would be incurred during this period due to a noncost reflective tariff, declares Jaffer.
Eskom announced last month that it might have to resort to selling bonds and incurring long-term debt from development banks to counter its financial shortfall.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation