More Stage 6 loadshedding as breakdowns approach 19 000 MW

The Tutuka power station

The Tutuka power station

Photo by Creamer Media

3rd May 2023

By: News24Wire

  

Font size: - +

Stage 6 loadshedding will be implemented from 16:00 on Tuesday until 05:00 on Thursday, Eskom said in a statement. 

After that, stages will vary between 4 and 6 until late on Friday. 

Breakdowns are currently at 18 972 MW of generating capacity, while 3 222 MW are out of service for planned maintenance. 

"Over the past 24 hours a generation unit each at Camden and Tutuka power stations were taken out of service due to breakdowns. The delay in returning units to service at Arnot, Camden, Duvha, Kendal, Kriel, Lethabo, Matimba, Matla and Tutuka power stations continues to add to the current capacity constraints.

"The team is working around the clock to ensure that generating units are returned to service as soon as possible," Eskom said.

Edited by News24Wire

Comments

Showroom

Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 
Alcohol Breathalysers
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 21 February 2025
Magazine round up | 21 February 2025
21st February 2025
BOLSTERING PRESENCE
The project is set to bolster Namibia’s position as one of the world’s leading uranium producers
Uranium mine moving closer to production
21st February 2025 By: Simone Liedtke

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:1.144 4.251s - 146pq - 3rq
Subscribe Now