Nornickel to shift part of nickel output to copper plant during repairs
Russian metals producer Nornickel plans to start experimental nickel smelting at its copper plant this year to maintain output during a major furnace reconstruction scheduled for 2027, a company vice president said.
The innovative move will allow the company to keep up nickel production during the overhaul.
Nornickel, the world's biggest palladium producer and a major supplier of high-grade nickel, plans to overhaul the smelting furnace at the Nadezhda Metallurgical Plant in the Arctic city of Norilsk in 2027, Alexander Leonov, head of the company's Norilsk unit, told the Norilsk TV channel on Thursday.
The shutdown will last about 270 days and temporarily remove roughly half of the plant's capacity, he said.
To offset the outage, Nornickel plans to convert part of its copper plant to produce nickel matte instead of copper - an "unconventional solution", Leonov said. The company is preparing production lines for the switch and aims to start pilot industrial tests this year.
Nornickel said in 2024 that it intended to close its Arctic copper plant and move copper production to China by mid-2027. Talks with Chinese partners are ongoing, according to a participant in a company conference call on Thursday.
The company expects nickel output of between 193 000 metric tons and 203 000 tons in 2026, roughly in line with 2025. Palladium output is forecast at between 2.415-million ounces and 2.465-million ounces, down by up to 11% year on year.
Nornickel's main shareholder and CEO Vladimir Potanin has previously said recent production declines are temporary, citing depleted ore reserves, the switch to non-Western equipment suppliers and the loss of some markets. He expects output to stabilise by 2028.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation