Orom-Cross graphite project, Uganda – update


Photo by Blencowe Resources
Name of the Project
Orom-Cross graphite project.
Location
Uganda.
Project Owner/s
Graphite, nickel and copper developer Blencowe Resources.
Project Description
A prefeasibility study (PFS) has highlighted an exceptional long-life project that delivers considerable returns over an initial life-of-mine of 14 years.
An estimated 600 000 t/y of ore will be mined from the commissioning date and this will increase to 2.4-million tonnes a year by the time the project is fully ramped up in Year 10.
Mining will be free-dig, with no drill-and-blast required. Initial ore will come from saprolite (clay) at an average depth of about 15 m to 20 m. Both deposits (Northern syncline and Camp lode) identified in the drilling programmes will be mined and a composite blend of both will be fed into the processing plant that will be built on site.
An initial 36 000 t/y of end-product will be delivered from the plant as concentrates, which will increase in two additional stages to 147 000 t/y once the mine is fully ramped up.
Further resources, higher production volumes and an extended mine life can all be obtained at any stage by drilling additional ready-targets. This, however, is not currently considered a priority.
The processing flowsheet comprises a flash and rougher flotation stage, followed by a primary cleaning circuit with a polishing mill and three stages of cleaner flotation. The intermediate concentrate is classified and then further upgraded in secondary cleaning circuits using stirred media mills, followed by cleaner flotation.
Orom-Cross will deliver at least five different end-products, characterised by +50 mesh, + 80 mesh, +100 mesh, +150 mesh and -100 mesh. These products will have different markets and will be branded and packaged on site.
Initially, transport to port will be by road, but it is expected that a rail option might be available by 2025, further reducing logistics costs.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at an 8% discount rate, of $482-million and an internal rate of return of 50%.
Capital Expenditure
The initial capital requirement has been lowered by 23%, to $62-million, since the preliminary economic assessment was announced in 2021.
Planned Start/End Date
First production is expected in 2026.
Latest Developments
Blencowe has completed an initial hydropower study for its graphite project.
The study has confirmed the availability of abundant, low-cost and renewable hydropower from the Ugandan national grid, providing a strategic advantage for the project's future mining and processing operations.
This marks a major step towards Blencowe's commitment to sustainability and its ambition to deliver a net-zero graphite operation.
Key findings of the study include plentiful renewable energy, whereby two high-capacity power transmission spurs extend to the regional grid near Orom-Cross, one from the Bujagali hydroelectric dam, in Jinga, and the other from the Isimba hydroelectric dam, both located on the Nile river.
This ensures a reliable supply of renewable energy to Orom-Cross, including redundancy, Blencowe has said.
Additionally, the study shows that Uganda's hydropower tariffs are significantly lower than regional African comparisons, positioning Orom-Cross as one of the lowest-cost graphite producers globally.
Blencowe is now working towards securing a long-term power purchase agreement with Uganda Electricity Transmission Company Limited to formalise the supply of low-cost hydroelectricity.
Orom-Cross will require 12 MW for Phase 2 commercial-scale production, scaling to 40 MW at full ramp-up, making power a critical cost factor.
Key Contracts, Suppliers and Consultants
Battery Limits (PFS); IMO (technical testwork); and CPC Engineering (DFS).
Contact Details for Project Information
Blencowe Resources, tel +44 1624 681 250 or email info@blencoweresourcesplc.com.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation