https://newsletter.mw.creamermedia.com
Africa|Consulting|Copper|Design|Gas|Gold|Infrastructure|Installation|Mining|Modular|Platinum|PROJECT|Resources|Services|srk|SRK Consulting|Surface|Underground|Waste|Water|WSP|Drilling|Infrastructure|Waste|Operations
Africa|Consulting|Copper|Design|Gas|Gold|Infrastructure|Installation|Mining|Modular|Platinum|PROJECT|Resources|Services|srk|SRK Consulting|Surface|Underground|Waste|Water|WSP|Drilling|Infrastructure|Waste|Operations
africa|consulting-company|copper|design|gas|gold|infrastructure|installation|mining|modular|platinum|project|resources|services|srk|srk-consulting|surface|underground|waste-company|water|wsp|drilling|infrastructure|waste|operations

Platreef palladium/rhodium/nickel/platinum/copper/gold project, South Africa – update

Image of Platreef project underground

Photo by Ivanhoe Mines

25th July 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Platreef palladium/rhodium/nickel/platinum/copper/gold project.

Location
The Platreef project hosts an underground deposit of thick platinum group metals (PGMs), nickel, copper and gold mineralisation on the northern limb of the Bushveld Igneous Complex, in Limpopo, South Africa.

This is about 280 km north-east of Johannesburg and 8 km from the town of Mokopane.

On the northern limb, PGM mineralisation is primarily hosted within Platreef, a mineralised sequence traced for more than 30 km along strike.

Project Owner/s
Diversified mining company Ivanhoe Mines indirectly owns 64% of the Platreef project through its subsidiary, Ivanplats, and is directing all mine development work.

The South African beneficiaries of the approved broad-based black economic-empowerment structure have a 26% stake in the project.

The remaining 10% is owned by a Japanese consortium comprising Itochu Corporation; Japan Oil, Gas and Metals National Corporation; Itochu affiliate ITC Platinum Development; and Japan Gas Corporation.

Project Description
The Platreef Mine has the potential to be a significant platinum, palladium, rhodium, and gold producer for many generations to come. The 35-year mine life, reflected in the 4.1-million-tonne-a-year feasibility study, is based only on indicated mineral resources using drilling across about one-third of Platreef mine’s licence package, with mineralisation open in multiple directions.

The project, within the Platreef’s southern sector, comprises two contiguous properties: Turfspruit and Macalacaskop. Turfspruit, the northernmost property, is contiguous with, and along strike from, Anglo Platinum’s Mogalakwena group of mining operations and properties.

The mining of the Platreef deposit will occur between 700 m and 1 200 m depth.

The mining areas will be accessed by each of the shafts to the three main underground access levels (750 m, 850 m, and 950 m levels).

Shaft 1 has a nameplate hoisting capacity of up to one-million tonnes a year. Shaft 2 will have a hoisting capacity of eight-million tonnes a year and will be one of the largest and highest-capacity shafts in Africa.

Shaft 3 will provide an additional four-million tonnes a year of hoisting capacity.

Once Shaft 3 is operational, the nameplate hoisting capacity of Shaft 1 will be temporarily decreased to hoist only labour and materials, while Shaft 3 hoists exclusively ore and waste rock.

The hoisting capacity of Shaft 1 will return to its original one-million tonnes a year once Shaft 2 is operational.

Each of these main levels provides access for labour, and materials and ore transfer, to the hoisting shafts.

The main access levels also connect to the interlevel development areas that access the stoping (production mining) areas.

Mining will be performed using highly productive mechanised methods, such as longhole stoping and drift-and-fill, using cemented backfill for maximum ore extraction

The phased expansion of PGM and base-metal production at Platreef will be achieved through the modular expansion of the concentrators. Every concentrator module will be designed and built using the same process design.

Phase 1 has a concentrator design capacity of 770 000 t/y.

The 2025 feasibility study on the Phase 2 expansion proposes a new 3.3-million-tonne-a-year concentrator module, built alongside the Phase 1 module, increasing the total Phase 2 processing capacity to 4.1-million tonnes a year – a near five-fold increase in 3PE+Au production to more than 460 000 oz of 3PE+Au, plus an estimated 9 000 t of nickel and 6 000 t of copper. The feasibility study estimates a life-of-mine (LoM) of 35 years.

The Phase 3 preliminary economic assessment (PEA) comprises a further two 3.3-million-tonne-a-year concentrator modules, built sequentially and located alongside the Phase 1 and 2 modules, which increases the total Phase 3 concentrator capacity to 10.7-million tonnes a year.

This expansion further doubles the annualised 3PE+Au production to more than one-million ounces of 3PE+Au, plus an estimated 22 000 t of nickel and 13 000 t of copper. The PEA estimates a 29-year LoM.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The 4.1-million tonne-a-year 2025 feasibility study generates an after-tax net present value (NPV), at an 8% discount rate, of $1.4-billion and an internal rate of return (IRR) of 20%, with a payback of 7.8 years.

The PEA generates an after-tax NPV, at an 8% discount rate, of $3.2-billion and an IRR of 25%, with a payback of 8.7 years.

Capital Expenditure
The 2025 feasibility estimates initial capital expenditure of $1.24-billion. The PEA estimates expansion capital of $803-million.

Planned Start/End Date
Phase 1 production is expected to start in the fourth quarter of 2025, with Phase 2 expansion accelerated to 2027.

The two additional 3.3-million-tonne-a-year concentrator modules in Phase 3 are expected to come online in 2030 and 2032.

Latest Developments
The project is progressing as planned, with the Phase 1 concentrator set to start production in the fourth quarter of this year.

Underground development of the Flatreef orebody started on April 30, 2025, at the 850 m level, as previously announced on May 8, 2025. Since then, 43 m of ore development had been completed, Ivanhoe reported in July. The pace of this development is expected to accelerate to 80 m a month. Additionally, reef development at the 750 m level is scheduled to start in October 2025.

All development ore is being brought to the surface and stored. The Ivanplats team plans to accumulate a stockpile of about 60 000 t of ore before feeding it into the Phase 1 concentrator. Initially, the concentrator will primarily use this development ore. Full-scale production mining (stoping) is expected to start in the first quarter of 2026, once Shaft 3 is completed. Over time, the amount of ore from stoping will increase as the project ramps up, reducing reliance on development ore.

Meanwhile, the underground delineation drilling programme, which started last year, is proceeding well. The first ore block at the 850 m level, where initial stoping will occur, has been drilled, and the assay results align well with Ivanplats' grade models, the company has reported.

Equipping of Shaft 3 is also on schedule and is expected to be ready for hoisting ore in the first quarter of 2026. The 5.1-m-diameter barrel support for the shaft is complete from the surface down to its 950 m depth, and the excavation for the shaft loading box is also complete. Work on the headgear assembly and the installation of the rock winder is well under way, with the mechanical installation of the rock winder nearly complete.

Key Contracts, Suppliers and Consultants
OreWin – Australia (overall report preparation and economic analysis, mineral reserve estimation and mine plan); Mine Technical Services – US (mineral resource estimation); SRK Consulting – South Africa (mine geotechnical recommendations); DRA Global – South Africa (process and infrastructure); and WSP – South Africa (water and tailings management).

Contact Details for Project Information
Ivanhoe Mines, tel +27 11 088 4300 or email info@ivanhoemines.com.

Edited by Creamer Media Reporter

Comments

Showroom

Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 
Flameblock
Flameblock

FlameBlock is a proudly South African company that engineers, manufactures and supplies fire intumescent and retardant products to the fire...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 25 July 2025
Magazine round up | 25 July 2025
25th July 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.202 0.337s - 129pq - 2rq
Subscribe Now