Prominent Hill copper/gold/silver mine expansion, Australia – update

Image of Prominent Hill mining operation

Photo by OZ Minerals

13th January 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Prominent Hill copper/gold/silver mine expansion.

Location
Gawler Craton, in South Australia.

Project Owner/s
Copper/gold miner OZ Minerals.

Project Description
An update on the Prominent Hill expansion study has shown that the installation of a 1 360 m, 7.5-m-diameter vertical shaft is technically and economically feasible, with capital investment consistent across the interim and strengthened cases.

Construction of the shaft is at this stage assumed to be a conventional blind sink.

A shaft will provide access to the deeper orebody beneath the current ore reserves boundary and exploration opportunities beyond the current mineral resource limits.

Shaft hoisting is the key enabler that will facilitate increased mine production. The company approved the construction of a hoisting shaft at the mine in August 2021. The Wira shaft would extend the mine life from the current nine years to 15 years, until 2036, at six-million tonnes a year.

The miner has since reported that project optimisation works have identified the opportunity to increase the hoisting shaft capacity by 8%, from six-million tonnes a year to 6.5-million tonnes a year.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
A$600-million.

Planned Start/End Date
The Wira shaft mine expansion project was approved in August 2021, with works well progressed and scheduled for completion in 2024.

Latest Developments
Takeover target OZ Minerals has reported an ore reserve increase at its Prominent Hill underground operation.

OZ Minerals has reported a near 23% increase to the Prominent Hill underground ore reserve, which now totals 59-million tonnes at 1.4% copper equivalent, extending the mine life by two years to at least 2038.

The project has a total resource estimate of about 180-million tonnes, containing 1.6-million tonnes of copper, 4.5-million ounces of gold and 14-million ounces of silver.

Key Contracts, Suppliers and Consultants
AECOM Australia, AGC Consulting, AMC Consultants, Ausenco, BBE Consulting, Beck Engineering Australasia, Boart Longyear, Byrnecut, Coffey, Convergen, D Why, EMM, Emtek, Golders, John Thompson Inclusive, Keaveney Consulting, Land and Water Consulting, Loesche, MCA, Mine Fill Services, Minset, More Space for Light, Newcrest Telfer Operations, Newmont Tanami Operations, Noble Environs, Pete Holliday, Redpath, Pells Sullivan Meynink, RUC, SAGE Automation, SRK Consulting, Stantec International Consulting, Strategy Focused Innovation, Woodgrove and Xylem Water Solutions (expansion study); and Hatch, IA Engineering, Optiro, SimSAGe, Stantec International Consulting, Strategy Focused Innovation and SRK International (peer review).

Contact Details for Project Information
OZ Minerals, tel +61 8 8229 6600 or email info@ozminerals.com.

Edited by Creamer Media Reporter

Comments

 

Showroom

Alcohol Breathalysers
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 
M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Minerals Council South Africa CEO Mzila Mthenjane
Minerals Council optimistic about ongoing MPRDA review
13th December 2024 By: Marleny Arnoldi
Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:1.368 1.543s - 129pq - 2rq
Subscribe Now