Name of the Project
Rincon lithium carbon plant.

Location
Salta province, Argentina.

Project Owner/s
Rio Tinto.

Project Description
Rio Tinto plans to develop a small starter battery-grade lithium carbonate plant with a capacity of 3 000 t/y.

The project includes early works to support a full-scale operation, including power line and associated substations, a construction camp and an airstrip.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
$190-million.

Planned Start/End Date
First saleable production is expected in 2024.

Latest Developments
The development of the lithium carbonate starter plant continues to progress, with construction activities more than 70% complete. 

Commissioning of medium- and low-voltage substations has started, and Rio Tinto continues to expect first production from the starter plant by the end of 2024. 

The feasibility study for full-scale operation is nearing completion, with a final investment decision expected in the fourth quarter of 2024. 

Rio Tinto reports in its results for the third quarter ended September 30, 2024, that it continues to engage with communities, the province of Salta and the government of Argentina to ensure an open and transparent dialogue with stakeholders about the works under way.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Rio Tinto, tel +44 20 7781 2000.

Edited by Creamer Media Reporter

Comments

Latest Multimedia

Martin Creamer talks about safety, ruthenium and a new palladium centre plan.
On-The-Air (18/04/2025)
Updated 6 hours ago By: Martin Creamer

Latest News

Magazine round up | 18 April 2025
Magazine round up | 18 April 2025
18th April 2025

Showroom

The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 
Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Hillside Aluminium smelter in South Africa’s KwaZulu-Natal.
Hillside Aluminium guiding unchanged output for 2025 financial year
17th April 2025 By: Martin Creamer
Andrada CEO Anthony Viljoen.
Andrada looking to opening more mines in Namibia
16th April 2025 By: Martin Creamer
Resources Watch
Resources Watch
16th April 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.051 0.18s - 127pq - 2rq
Subscribe Now