Sage Plain potash project, US

Image of potash ore

Photo by ©Bloomberg

21st November 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Sage Plain potash project.

Location
San Juan County, Utah, in the US.

Project Owner/s
Potash exploration company Sage Potash.

Project Description
A preliminary economic assessment (PEA), published in September 2025, has highlighted the potential for robust project economics, a significant domestic resource base, and growth potential to establish a scalable and sustainable potash production hub in the US.

The PEA estimates an inferred mineral resource of 298-million million tonnes in in situ sylvinite, equating to about 118-million tonnes of potassium chloride within a 2 400 m radius of drilled wells.

The proposed project includes the construction of a 300 000 t/y potash plant with an initial development plan of seven caverns, expanding to 15 caverns over the first five years of production.

Total production over the 20-year life-of-mine is estimated at 5.63-million tonnes.

Potential Job Creation
The project is expected to create about 100 jobs.

Net Present Value/Internal Rate of Return
The PEA highlights an after-tax unlevered net present value, at an 8% discount rate, of $502-million and an internal rate of return of 39%, with a payback within five years.

Capital Expenditure
Initial capital expenditure is estimated at $155-million.

Planned Start/End Date
Not stated.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
RESPEC (PEA).

Contact Details for Project Information
Sage Potash, tel +1 236 521 1521 or email info@sagepotash.com.
 

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Latest News

CEO Mike Henry delivering BHP's half-year results.
Copper becomes BHP’s biggest earnings driver
17th February 2026 By: Mariaan Webb

Showroom

Essentra Components
Essentra Components

We are responsible manufacturers of essential components. Manufacturing 80 million parts a week, we have over 1 billion parts in stock.

VISIT SHOWROOM 
ATI Systems
ATI Systems

ATI systems comprises five divisions: electrical assemblies, drives and controls, feedback sensors, enclosures, and strip guiding.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (13/02/2026)
13th February 2026 By: Martin Creamer
Magazine round up | 13 February 2026
Magazine round up | 13 February 2026
13th February 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.183 0.325s - 128pq - 2rq
Subscribe Now