Thacker Pass lithium project, US – update

Drill core from Thacker Pass

Photo by Lithium Americas Corp

27th February 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Thacker Pass lithium project.

Location
Humboldt County, Nevada, in the US.

Project Owner/s
North American lithium company Lithium Americas Corp (LAC).

Project Description
LAC aims to extract lithium at Thacker Pass from a large clay deposit, something that has never been done before at commercial scale.

The project is targeting 80 000 t/y of battery-quality lithium carbonate production capacity in two phases of 40 000 t/y each.

Thacker Pass will have a mine life of 40 years.

The mine is slated to be a key supplier to General Motors.

Potential Job Creation
The site workforce was estimated at 950 people on December 31, 2025. This is expected to increase to about 1 800 at peak construction in 2026, with 1.69-million workhours completed in 2025 without a serious injury or lost-time incident. The Workforce Hub became partially operational in September 2025 and had nearly 700 residents by February 13, 2026.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at an 8% discount rate, of $4.95-billion and an internal rate of return of 21.2%.

Capital Expenditure
The mine's cost had been increased from a previous estimate of $2.27-billion to nearly $2.93-billion, as a result of higher engineering costs, an agreement to use union labour and the company's decision to build a housing facility for workers and their families in the remote region. For 2026, the company has guided total Phase 1 capital expenditure from $1.3-billion to $1.6-billion.

Planned Start/End Date
Lithium Americas is targeting milestones, including the delivery of major long-lead equipment in the first half of 2026, high-voltage power line commissioning in the second quarter of 2026, completion of main concrete in the third quarter of 2026, and early commissioning in the fourth quarter 2026, while maintaining a target of mechanical completion in late 2027 (with ramp-up in 2028).

Latest Developments
Lithium Americas has reported that Phase 1 construction is well under way, with detailed engineering about 93% complete and procurement about 60% complete as at December 31, 2025. 

Key Contracts, Suppliers and Consultants
Aquatech International (magnesium sulphate and lithium carbonate chemical plants); Bechtel Corporation (engineering, procurement and construction management); EXP Global Inc (engineering, procurement, construction support, commissioning and startup services for the sulphuric acid plant).

Contact Details for Project Information
Lithium Americas Corp, email info@lithiumamericas.com.

 
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Latest News

BHP CEO Mike Henry
Henry says BHP has no plans to become copper pure play
Updated 1 hour 51 minutes ago By: Mariaan Webb

Showroom

Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 
ACTOM
ACTOM

Your one-stop global energy-solution partner

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 27 February 2026
Magazine round up | 27 February 2026
27th February 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.065 0.224s - 106pq - 2rq
Subscribe Now