Thunderbird commissioning starts

18th September 2023

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Commissioning of the process plant at the Thunderbird mineral sands project, in Western Australia, is under way with owner Sheffield Resources saying the project is tracking within its original budget of A$484-million.

“With commissioning activities well underway at Thunderbird, we are on track to deliver first ore production during the next quarter,” said executive chairperson Bruce Griffin.

“Our expenditure forecast remains within our original final investment decision budget of A$484-million, which is an outstanding achievement and a credit to the Kimberley Mineral Sands team and contractors associated with the Thunderbird project. We look forward to announcing first production in the forthcoming quarter and forecast first shipment of product in the first quarter of 2024.”

The two-stage Thunderbird development pathway sees the initial Stage 1 mining and processing feed rate forecast at 1 085 t/h at the wet concentrate plant (WCP), with Stage 2 doubling the WCP feed rate to 2 170 t/h targeted during Year 5 of operations.

Stage 1 and 2 of operations is estimated to produce 1.4-million tonnes a year of zircon and ilmenite concentrates over an estimated 36-year life-of-mine.

Edited by Creamer Media Reporter

Comments

Showroom

Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 
Avlock International
Avlock International

Avlock International is a leading manufacturer and distributor of Specialized Fastening Systems.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:1.287 1.392s - 127pq - 2rq
Subscribe Now