https://newsletter.mw.creamermedia.com
Design|Energy|Engineering|Exploration|generation|Mining|Power|PROJECT|Resources|Power Generation|Power-generation|Operations
Design|Energy|Engineering|Exploration|generation|Mining|Power|PROJECT|Resources|Power Generation|Power-generation|Operations
design|energy|engineering|exploration|generation|mining|power|project|resources|power-generation|power-generation-industry-term|operations

Tiris uranium project, Mauritania – update

Image of periodic table symbol for uranium

24th January 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Tiris uranium project.

Location
Mauritania.

Project Owner/s
Uranium exploration company Aura Energy.

Project Description
In September 2024, Aura Energy reported in an update to the February 2024 front-end engineering design (FEED), a 44% increase in life-of-mine (LoM) production from 30.1-million pounds a year to 43.5-million pounds of triuranium octoxide (U3O8) in the FEED. This follows the upgrading of the project's mineral resource to 91.3-million pounds of U3O8.

The update also noted an increase in the project’s mine life from 17 years to 25 years.

The processing plant will average 1.8-million pounds a year of U3O8 from the two-million pound-a-year-capacity U3O8 process plant.

Envisaged is a shallow free-dig openpit mining and beneficiation operation, with the operation delivering a high-grade leach feed averaging 2 217 parts per million (ppm) U3O8, an increase from 1 997 ppm U3O8 (over first five years) in the FEED. This remains overall about the same at 1 752 ppm U3O8 from 1 743 ppm U3O8 in the FEED at a very low average cost of $9.16/lb U3O8.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Aura reported in September 2024 that economics on the project had improved, with the net present value (NPV) having increased by 29% to $499-million, compared with $388-million set out in the February FEED study. The after-tax internal rate of return (IRR) is now estimated at 39%, compared with the 36% estimated in February.

Payback has decreased by 10% to 2.25 years.

Capital Expenditure
$230-million.

Planned Start/End Date
First production at the project is targeted for 2026/27.

Latest Developments
Aura Energy has undertaken an assessment of the opportunities for future capacity expansion. The assessment demonstrates the significant growth opportunity at the project through a future expansion of the project from Stage 1 cash flows, improving confidence in the inferred mineral resources and further exploration success.

The assessment used inputs from the September production target update and the recently expanded 91.3-million-pound U3O8 mineral resource.

Alternative production targets have been based on an analysis of opportunities to accelerate production in Year 3 of operation, without any other material changes to the underlying assumptions or levels of confidence – not replacing the base case, but rather demonstrating optionality for the Tiris project once in operation. 

Options have been analysed to expand production capacity in the third year of operations – from the initial development plan of a 4.1-million-tonne-a-year mine rate producing about two-million pounds of U3O8 – by accelerating the mining rate and increasing production capacity.

Production scenarios have been assessed for mining rates of 6.25-million tonnes a year producing about three-million pounds a year of U3O8, and 8.2-million tonnes a year producing about four-million pounds a year of U3O8.

The first option returned the highest NPV and improved economics.

Results included an NPV of about $544-million (A$836-million) – an increase of 9% on the base case – and an IRR of about 45% after-tax and payback of about 2.5 years.

Moreover, the option indicates high-margin average yearly after-tax cash flows over the LoM of about $86-million, an increase of 37% and average of about $116-million over the first five years of operations.

Additional development capital is fundable from cashflow.

Key Contracts, Suppliers and Consultants
Wood (basic engineering and early works definition programme); and ECG Engineering (power generation solution).

Contact Details for Project Information
Aura Energy, tel +61 3 9101 8551 or email info@auraenergy.com.au.
 

Edited by Creamer Media Reporter

Comments

Showroom

M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 
Tractor & Grader Supplies
Tractor & Grader Supplies

Tractor & Grader Supplies (TGS™): Your Trusted, Genuine Source for New Replacement Parts for Earthmoving, Construction and Mining Machinery

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 21 February 2025
Magazine round up | 21 February 2025
21st February 2025
BOLSTERING PRESENCE
The project is set to bolster Namibia’s position as one of the world’s leading uranium producers
Uranium mine moving closer to production
21st February 2025 By: Simone Liedtke

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.05 0.18s - 129pq - 2rq
Subscribe Now