Kariba Dam rehab project making progress
RISING LEVELS The lake levels, which should generally be in a decreasing trend at this time of the year, have continued to record a steady rise
Binational organisation the Zambezi River Authority (ZRA) is progressing work at the Kariba Dam Rehabilitation Project (KDRP).
The authority says that ongoing KDRP works comprise two components, namely reshaping of the plunge pool and the refurbishment of the spillway gates.
The project aims to enhance the structural integrity of the Kariba dam wall for efficient power generation for the benefit of Zambia and Zimbabwe and the Southern African region as a whole.
The reshaping of the plunge pool, which started in May 2017 and is now 60% complete, involves excavation of the rock in the pool to increase the pool volume and minimise erosion, which can undercut the dam’s foundations.
These works, which are being undertaken by French civil engineering construction company Razel Bec, are expected to be completed before the end of 2024.
The work comprises the construction of a downstream cofferdam to enable the blasting and excavation of an estimated 300 000 m3 of rock from the downstream end and north and south bank sides of the pool, the ZRA says.
“This will create a new pool profile that will dissipate the energy of the water jets from the floodgates to nonerosive levels, as well as reduce turbulence by guiding the spilling water in the downstream direction, thereby avoiding any backward erosion towards the dam’s foundations in the process.”
Meanwhile, the spillway refurbishment works, which a consortium comprising GE Hydro and Freyssinet International started in September 2019, aim to ensure free movement of the gates used to shut the upstream opening of the floodgates when they are being maintained.
An emergency gate, to be used in emergency situations such as where a gate fails to close after spilling, together with a lifting crane, will be fabricated and installed. The hoisting equipment for the spilling gates will also be renewed.
The activities are expected to be completed in 2024.
“The spillway refurbishment contractor is currently working on the establishment of construction site facilities, as well as the fabrication of the electromechanical equipment required for execution of the works through specialist subcontractors,” the ZRA comments.
“The manufacturing progress details are twofold. Firstly, the manufacturing of stop logs is being done in China by the subcontractor, Sinohydro Bureau 8. The works are progressing well and delivery of the first components is expected by mid- February 2021. Secondly, the manufacturing of the needle cofferdam, which is required to isolate the works, is being undertaken in Poland by the subcontractor, APC Presmet.”
Meanwhile, the
ZRA will maintain the 30-billion cubic metres of water allocated for power generation operations at Kariba for 2021, shared equally between Kariba North Bank Power Station and Kariba South Bank Power Station.
The allocation is based on the Meteorological Authorities’ projections of normal to above-normal rains for the ongoing 2020/21 rainfall season.
“In line with the seasonal forecast released by the twenty-fourth annual Southern Africa Regional Climate Outlook Forum in August 2020, the bulk of the Southern African Development Community region in general and the Kariba catchment in particular is poised to receive normal to above-normal rainfall for the first quarter of 2021,” the ZRA points out.
Between December 22 and January 18, the lake levels increased by 0.40 m, or 0.08%, which brought the overall lake levels to 3.21 m above the minimum operating level (MOL) of 475.50 m.
“This 3.21 m above the MOL translates to 14.55-billion cubic metres of usable water storage currently in the lake.
“It is very encouraging to note that the lake levels, which should generally be in a decreasing trend at this time of the year, have continued to record a steady rise, owing to increased rainfall activity on and around the lake, leading to a lake level of 478.71 m, with 22.45% live/usable storage on January 18. Last year on the same date, the lake level was lower at 476.71 m with 8.36% usable storage,” the authority concludes.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation