Ancuabe costs lower as output increased
PERTH (miningweekly.com) – An updated definitive feasibility study (DFS) into the Ancuabe graphite project, in Mozambique, has resulted in a decrease in up-front capital expenditure (capex) and an increase in expected yearly production.
ASX-listed Triton Minerals on Tuesday said that the updated DFS had reduced the up-front capex from the $99.1-million previously estimated, to $90.3-million, while increasing processing plant throughput from 1-million tonnes a year to 1.2-million tonnes a year, resulting in graphite production increasing from 60 000 t/y to 70 000 t/y.
Triton last year re-committed itself to the full-scale development of the Ancuabe project, as envisioned in the original 2017 DFS, which estimated a mine life of 27 years.
The decision to pursue a large-scale development came after Triton completed a strategic review and desktop study in 2022 considering various alternatives to bring the Ancuabe project into production in the short term, including a Stage 1 development of a commercial pilot plant producing 5 000 t/y to 8 000 t/y of graphite concentrate, which would later be expanded to the Stage 2 project targeting the 60 000 t/y production.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation