https://newsletter.mw.creamermedia.com
Components|Construction|Design|Logistics|PROJECT|Roads|Steel
Components|Construction|Design|Logistics|PROJECT|Roads|Steel
components|construction|design|logistics|project|roads|steel

BCI flags A$500m cost blow-out and delayed production

Image shows potash ore

Photo by Bloomberg

20th June 2023

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Potash developer BCI Minerals has flagged a A$500-million cost blow-out at its Mardie potash project, in Western Australia, while also warning of delays to first production.

The company on Tuesday revealed the results of its design and cost review, which has updated the cost estimate for Mardie to A$1.62-billion, with a base estimate of A$1.42-billion and a contingency of A$208-million.

This is significantly higher than the A$913-million cost previously estimated for the project.

MD David Boshoff said in a presentation on Tuesday that the cost and design review had identified cost pressures across a number of areas, a key one being the civil works, which had impacted the cost of the ponds, roads, transfer stations, crystallisers and jetty pad.

“The key driver of these costs were from geotechnical conditions of borrow material, which increased haul distances that impacted demand for diesel, labour, accommodation and flights, all of which were subject to market cost increases.

“The salt plant, while improved in design, increased in quantity of steel required, and also suffered from the increased cost of underlying components due to supply logistics and labour shortages driven by Covid. The design and cost review process has increased the robustness of the project design and confidence in the cost forecast,” he said.

Boshoff told shareholders that while significant work had been undertaken on the project scope to ensure that it was optimised and fit for purpose, the review process had retained the steady state production level of 5.35-million tonnes a year for salt and 140 000 t/y for sulphate of potash (SoP).

The timing of the first salt on ship and first SoP on ship, however, has both been delayed, with salt now targeted for mid-2026 and SoP mid-2027, instead of the initial target of the first quarter of 2024 and the first quarter of 2026 respectively.

“Mid-2026 lines up well with the salt marketing regimes in the Asian markets and allows trial cargoes to be conducted for the Mardie product during the first year of production to our key customers,” Boshoff said on Tuesday.

Construction at Mardie started in February 2022, and as of the end of March this year, BCI has spent a cumulative A$307-million on the project. Overall, construction progress is 22% complete, and to date A$551-million in contracts have been awarded.

The necessary approvals to finalise the construction of the project were progressing, Boshoff added.

The company said on Tuesday that although global costs had increased for construction, so too had the long run prices of both salt and SoP owing to an increase in market demand and an anticipated shortfall in supply. This had driven a 50% increase in the forecast earnings before interest, taxes, depreciation and amortisation at the project, which was now estimated at A$384-million at steady-state while the project now had an improved net present value of A$2.6-billion compared with the A$1.5-billion estimated at the time of the final investment decision.

“These key factors support BCI’s ability to secure an appropriate amount of project finance, and then to complete the equity raising process for Mardie. BCI expects to provide further information on project finance and its equity-raising process in coming months. BCI is considering equity raising at both BCI and project levels,” Boshoff said.

Discussions with financiers are progressing and BCI is targeting final documentation by the third quarter of this year to fund all capital except for the SoP plant. Debt finance for the SoP plant is targeted for late in 2024, on the completion of further design and cost development.

Edited by Creamer Media Reporter

Comments

Showroom

Victaulic
Victaulic

Since 1919, Victaulic’s innovative solutions and design services continue to increase construction productivity and reduce risk, ensuring projects...

VISIT SHOWROOM 
BOVA Safety Wear
BOVA Safety Wear

BOVA cemented their reputation in Africa by delivering high quality engineering through their range of safety footwear. 21 years after producing...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer
Magazine round up | 15 November 2024
Magazine round up | 15 November 2024
15th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:2.902 3.032s - 126pq - 2rq
Subscribe Now